Snip 3 05 06 85 electrical devices. Laying wires and cables in steel pipes

BUILDING REGULATIONS

ELECTRICAL DEVICES

SNiP 3.05.06-85

GOSSTROY USSR

MOSCOW 1988

DEVELOPED by VNIIproektelektromontazhem of the USSR Ministry of Assembly and Special Construction (V.K. N.I. Korotkov, E.G. Panteleev, Candidate of Technical Sciences Yu.A. Roslov, S.N. Starostin, A.K. V. Balanov, N.A. Voinilovich, A.L. Gonchar, N.M. Lerner), Sellenergoproekt of the USSR Ministry of Energy (G.F.Sumin, Y.V. , A.A. Koba).

INTRODUCED by the USSR Ministry of Assembly and Construction.

PREPARED FOR APPROVAL by the Glavtekhnormirovanie Gosstroy of the USSR (BA Sokolov).

With the entry into force of SNiP 3.05.06-85 "Electrical devices" SNiP III-33-76 *, SN 85-74, SN 102-76 * are no longer valid.

AGREED with the Glavgosenergonadzor of the USSR Ministry of Energy (letter of January 31, 1985, No. 17-58), GUPO of the USSR Ministry of Internal Affairs (letter of September 16, 1985, No. 7/6/3262), the chief sanitary doctor of the USSR Ministry of Health (letter of January 14, 1985 . No. 122-4 / 336-4).

When using a regulatory document, the approved changes in building codes and regulations should be taken into account and state standards published in the journal "Bulletin of Construction Technology", "Collection of changes to building codes and regulations" of the USSR State Construction Committee and the information index "USSR State Standards" of the State Standard.



These rules apply to the production of work during the construction of new, as well as during the reconstruction, expansion and technical re-equipment of existing enterprises for the installation and commissioning of electrical devices, including: electrical substations, distribution points and overhead power lines with a voltage of up to 750 kV, cable lines with a voltage of up to 220 kV, relay protection, power electrical equipment, indoor and outdoor electrical lighting, grounding devices.

The rules do not apply to the production and acceptance of work on the installation and commissioning of electrical devices of the subway, mines and mines, contact networks of electrified transport, signaling systems railway transport, as well as high-security premises nuclear power plants, which must be carried out in accordance with the departmental building codes approved in the manner established by SNiP 1.01.01-82.

The rules must be observed by all organizations and enterprises involved in the design and construction of new, expansion, reconstruction and technical re-equipment of existing enterprises.

1. GENERAL PROVISIONS

1.1. When organizing and performing work on the installation and commissioning of electrical devices, the requirements of SNiP 3.01.01-85, SNiP III-4-80, state standards, technical conditions, the Rules for the installation of electrical installations approved by the USSR Ministry of Energy, and departmental regulatory documents approved by established by SNiP 1.01.01-82.

Acting

d) a project for the production of works has been developed, the engineering and technical workers and foremen have been familiarized with the working documentation and estimates, organizational and technical solutions for the project for the production of works;

e) acceptance was carried out according to the act of the construction part of the object for the installation of electrical devices in accordance with the requirements of these rules and the labor protection measures provided for by the rules and regulations were carried out, fire safety and environmental protection in the course of work;

2.3. Equipment, products, materials and technical documentation should be transferred to installation in accordance with the contracts for capital construction and the relationship of organizations - general contractors with subcontractors.

2.9. Expired electrical equipment standard term storage specified in state standards or technical conditions, is accepted for installation only after pre-installation revision, defect correction and tests. The results of the work carried out must be entered in the forms, passports and other accompanying documentation, or an act of carrying out the indicated work must be drawn up.

2.11. For large and complex objects with a large volume of cable lines in tunnels, canals and cable half-floors, as well as electrical equipment in electrical rooms, the construction organization design should define measures for advanced installation (against the installation of cable networks) of internal fire-fighting water supply systems, automatic fire extinguishing and automatic fire extinguishing systems. alarms provided by the working drawings.

2.12. In electrical rooms (switchboards, control rooms, substations and switchgears, machine rooms, battery rooms, cable tunnels and channels, cable half-floors, etc.), clean floors with drainage channels, the necessary slope and waterproofing and finishing works (plastering and painting ), embedded parts were installed and installation openings were left, the lifting and handling mechanisms and devices provided for by the project were mounted, pipe blocks, holes and openings for the passage of pipes and cables, grooves, niches and nests were prepared in accordance with the architectural and construction drawings and the work production project, power supply for temporary electric lighting in all rooms is made.

Building regulations

Electrical devices SNiP 3.05.06-85

DEVELOPED by VNIIproekt elektromontazh by the USSR Ministry of Montazhspetsstroy

(V.K.Dobrynin, I.N.Dolgov - topic leaders, Candidate of Engineering Sciences V.A. Antonov, A.L. Blinchikov, V.V. Belotserkovets, V.A. Demyantsev, Candidate of Engineering Sciences

N.I. Korotkov, E.A. Panteleev, Candidate of Engineering Sciences Yu.A. Roslov, S.N. Starostin, A.K. Shulzhitsky), Orgenergostroem of the USSR Ministry of Energy (G.N. Elenbogen, N.V. Belanov, N.A. Voinilovich, A.L. Gonchar, N.M. Lerner), Sellenergoproekt of the USSR Ministry of Energy (G.F. Sumin, Yu.V. Nepomnyashchy), UGPI Tyazhpromelektroproekt Minmontazhspetsstroy of the Ukrainian SSR (E.G. Poddubny, A A. Koba).

INTRODUCED by the USSR Ministry of Montazhspetsstroy.

APPROVED by the decree of the USSR State Committee for Construction of December 11, 1985 No. 215

REPLACE SNiP III-33-76 *, SN 85-74, SN 102-76 *.

These rules apply to the production of work during the construction of new, as well as during the reconstruction, expansion and technical re-equipment of existing enterprises for the installation and commissioning of electrical devices, including: electrical substations, distribution points and overhead power lines with a voltage of up to 750 kV, cable lines with a voltage of up to 220 kV, relay protection, power electrical equipment, indoor and outdoor electrical lighting, grounding devices.

The rules do not apply to. production and acceptance of works on the installation and commissioning of electrical devices of the subway, mines and mines, contact networks of electrified transport, signaling systems of railway transport, as well as premises of strict regime of nuclear power plants, which must be carried out in accordance with departmental building codes approved in the manner established by SNiP 1.01.0182.

The rules must be observed by all organizations and enterprises involved in the design and construction of new, expansion, reconstruction and technical re-equipment of existing enterprises.

1. GENERAL PROVISIONS

1.1. When organizing and performing work on the installation and commissioning of electrical devices, the requirements of SNiP should be observed 3.01.01-85, SNiP III-4-80, state standards, technical conditions. Of the Rules for the Installation of Electrical Installations, approved by the USSR Ministry of Energy, and departmental normative documents approved in the manner prescribed by SNiP 1.01.01-82.

1.2. Installation and commissioning of electrical devices should be carried out in accordance with the working drawings of the main sets of drawings of electrical brands; on working documentation for electric drives; according to the working documentation of non-standardized equipment, carried out design organization; according to the working documentation of enterprises - manufacturers of technological equipment, supplying power and control cabinets with it.

1.3. Installation of electrical devices should be carried out on the basis of the use of nodal

and complete block construction methods, with the installation of equipment supplied in enlarged units that do not require straightening, cutting, drilling or other adjusting operations and adjustments during installation. When accepting the working documentation for the production of work, it is necessary to check that it takes into account the requirements for the industrialization of the installation of electrical devices, as well as the mechanization of work on laying cables, rigging and installing technological equipment.

1.4. Electrical work should be performed, as a rule, in two stages.

In the first stage, inside buildings and structures, work is carried out on the installation of support structures for the installation of electrical equipment and busbars, for laying cables and wires, installing trolleys for electric bridge cranes, installing steel and plastic pipes for electrical wiring, laying hidden wiring wires before plastering and finishing works, as well as work on the installation of external cable networks and grounding networks. The work of the first stage should be performed in buildings and structures according to the combined schedule simultaneously with the production of the main construction works, while measures should be taken to protect the installed structures and laid pipes from breakages and contamination.

In the second stage, work is performed on the installation of electrical equipment, laying cables and wires, busbars and connecting cables and wires to the terminals of electrical equipment. In the electrical rooms of the objects of the second stage, work should be performed after the completion of the complex of general construction and finishing works and after the completion of the installation of plumbing devices, and in other rooms and zones - after the installation of technological equipment, electric motors and other electrical receivers, installation of technological, sanitary pipelines and ventilation ducts ...

At small objects remote from the locations of electrical installation organizations, work should be carried out by field complex teams with the combination of two stages of their implementation in one.

1.5. Electrical equipment, products and materials should be delivered according to the schedule agreed with the electrical installation organization, which should provide for the priority delivery of materials and products included in the specifications for blocks to be manufactured on assembly and picking enterprises of electrical installation organizations.

1.6. The completion of the installation of electrical devices is the completion of individual tests of the mounted electrical equipment and the signing by the working commission of an act of acceptance of electrical equipment after an individual test. The beginning of individual tests of electrical equipment is the moment of introduction of an operating mode at a given electrical installation, announced by the customer on the basis of a notice from the commissioning and electrical installation organizations.

1.7. At each construction site during the installation of electrical devices, special journals should be kept for the production of electrical work in accordance with SNiP 3.01.01-85, and upon completion of the work, the electrical installation organization is obliged to transfer to the general contractor the documentation presented by the working commission in accordance with SNiP III-3-81. The list of acts and protocols of inspections and tests is determined by the VSN, approved in the established SNiP

1.01.01-82 ok.

2. PREPARATION FOR PRODUCTION OF ELECTRICAL INSTALLATION WORKS

2.1. The installation of electrical devices must be preceded by preparation in accordance with SNiP 3.01.01-85 and these rules.

2.2. Prior to the commencement of work at the facility, the following activities must be performed:

a) the working documentation was received in the quantity and within the timeframe determined by the Rules on construction contracts for capital

construction, approved by the decree of the Council of Ministers of the USSR, and the Regulations on the relationship of organizations, general contractors with subcontractors, approved by the USSR State Construction Committee and the USSR State Planning Committee;

b) the schedules for the supply of equipment, products and materials were agreed, taking into account the technological sequence of work, the list of electrical equipment installed with the involvement of the chief installation personnel of the supplier enterprises, the conditions for transporting heavy and large-sized electrical equipment to the installation site;

c) the necessary premises were taken to accommodate teams of workers, engineering and technical workers, a production base, as well as for storing materials and tools with the provision of labor protection measures, fire safety and environmental protection in accordance with SNiP 3.01.01-85;

Electrical Library / www.elec.ru

d) a project for the production of works has been developed, the engineering and technical workers and foremen have been familiarized with the working documentation and estimates, organizational and technical solutions for the project for the production of works;

e) the acceptance of the construction part of the object for the installation of electrical devices in accordance with the requirements of these rules has been carried out and the measures for labor protection, fire safety and environmental protection during the work are carried out as provided for by the rules and regulations;

f) performed by the general contractor general construction and auxiliary works stipulated by the Regulations on the relationship of organizations - general contractors with subcontractors.

2.3. Equipment, products, materials and technical documentation must be transferred for installation in accordance with the Rules on Contracts for Capital Construction and the Regulations on the Relationship of Organizations - General Contractors with Subcontractors.

2.4. When the equipment is accepted for installation, it is inspected, the completeness is checked (without disassembly), the availability and validity of guarantees are checked manufacturing enterprises.

2.5. The condition of the cables on the drums should be checked in the presence of the customer by means of an external examination. The results of the inspection are documented in an act.

2.6. When accepting prefabricated reinforced concrete structures of overhead lines (OHL), the following should be checked:

the dimensions of the elements, the position of the steel embedded parts, as well as the quality of the surfaces and appearance elements. The specified parameters must comply with GOST 13015.0-83, GOST

22687.0-85, GOST 24762-81, GOST 26071-84, GOST 23613-79, as well as PUE;

the presence on the surface of reinforced concrete structures intended for installation in an aggressive environment, waterproofing made at the manufacturer.

2.7. Insulators and line fittings must meet the requirements of the relevant state standards and specifications. When accepting them, you should check:

availability of a manufacturer's passport for each batch of insulators and linear fittings, certifying their quality;

the absence of cracks, deformations, cavities, chips, damage to the glaze on the surface of the insulators, as well as swaying and turning of the steel reinforcement relative to the cement embedding or porcelain;

the absence of cracks, deformations, cavities and damage to galvanized steel and threads in linear reinforcement.

It is allowed to paint over minor damages of galvanized steel.

2.8. Elimination of defects and damages discovered during the transfer of electrical equipment is carried out in accordance with the Rules on Contracts for Capital Construction.

2.9. Electrical equipment, for which the standard storage period specified in state standards or technical conditions has expired, is accepted for installation only after a pre-installation audit, correction of defects and tests. The results of the work carried out must be entered in the forms, passports and other accompanying documentation, or an act of carrying out the indicated work must be drawn up.

2.10. Electrical equipment, products and materials accepted for installation should be stored in accordance with the requirements of state standards or technical specifications.

2.11. For large and complex objects with a large volume of cable lines in tunnels, channels

and of cable semi-floors, as well as electrical equipment in electrical rooms in the construction organization project, measures for advanced installation (against the installation of cable networks) of internal fire-fighting water supply systems, automatic fire extinguishing and automatic fire alarm systems, provided for by the working drawings, should be determined.

2.12. In electrical rooms (switchboards, control rooms, substations and switchgears, machine rooms, battery rooms, cable tunnels and channels, cable half-floors, etc.), clean floors with drainage channels, the necessary slope and waterproofing and finishing works (plastering and painting ), embedded parts were installed and assembly openings were left, the lifting and handling mechanisms and devices provided for by the project were mounted, pipe blocks, holes and openings for

Electrical Library / www.elec.ru

the passage of pipes and cables, furrows, niches and nests, a power supply for temporary electric lighting in all rooms is made.

2.13. In buildings and structures, heating and ventilation systems must be put into operation, bridges, platforms and structures of suspended ceilings provided by the project for the installation and maintenance of electric lighting installations located at a height, as well as fixing structures for multi-lamp lamps (chandeliers) weighing over 100 kg; laid outside and inside buildings and structures asbestos-cement pipes and pipes and pipe blocks for the passage of cables provided for by the working construction drawings.

2.14. Foundations for electrical machines should be handed over for installation with fully completed construction and finishing works, installed air coolers and ventilation ducts, with benchmarks and axial strips (measurements) in accordance with the requirements of SNiP 3.02.01-83 and these rules.

2.15. On the supporting (rough) surfaces of foundations, depressions of no more than 10 mm and slopes up to 1: 100 are allowed. Deviations in building dimensions should be no more than: in terms of axial dimensions in the plan - plus 30 mm, in elevation marks of the surface of the foundations (excluding the height of the grout) - minus 30 mm, in terms of the dimensions of the ledges in the plan - minus 20 mm, in terms of the dimensions of wells - plus 20 mm, along the marks of the ledges in the recesses and wells - minus 20 mm, along the axes of the anchor bolts in the plan - ± 5 mm, along the axes of the embedded anchor devices in the plan - ± 10 mm, along the marks of the upper ends of the anchor bolts - ± 20 mm.

2.16. Delivery and acceptance of foundations for the installation of electrical equipment, the installation of which is carried out with the involvement of the installation supervision personnel, is carried out jointly with representatives of the organization that carries out installation supervision.

2.17. At the end of the finishing work in the battery rooms, acid or alkali-resistant coatings of walls, ceilings and floors should be made, heating, ventilation, water supply and sewerage systems installed and tested.

2.18. Before the start of electrical work on open switchgears with a voltage of 35 kV and above, the construction organization must complete the construction of access roads, approaches and entrances, install bus and linear portals, build foundations for electrical equipment, cable channels with ceilings, fences around the switchgear, emergency discharge tanks oils, underground utilities and the planning of the territory is completed. In the structures of portals and foundations for the equipment, the embedded parts and fasteners provided for by the project must be installed, which are necessary for fastening the garlands of insulators and equipment. In cable ducts and tunnels, embedded parts must be installed for fastening cable structures and air ducts. The construction of a water supply system and other fire-prevention devices provided for by the project must also be completed.

2.19. Construction part of outdoor switchgear and voltage substations 330-750 kV should be accepted for installation for their full development, provided for by the project for the billing period.

2.20. Before the start of electrical work on the construction of overhead power lines with a voltage of up to 1000 V and above, preparatory work must be performed in accordance with SNiP

3.01.01-85, including:

Inventory structures were prepared at the locations of foreman's plots and temporary bases for storing materials and equipment; temporary access roads, bridges and assembly sites were built;

glades are arranged; the demolition of buildings and reconstruction of the intersected

engineering structures located on or near the overhead line route and interfering with the production of work.

2.21. The routes for laying the cable in the ground must be prepared for the beginning of its laying in the following volume: water is pumped out of the trench and stones, clods of earth, construction waste are removed; at the bottom of the trench there is a cushion of loosened earth; punctures were made in the ground at the intersection of the route with roads and other engineering structures, pipes were laid.

After laying the cables in the trench and the submission by the electrical installation organization of the act for the hidden work on laying the cables, the trench should be filled up.

2.22. Block sewerage routes for cable laying must be prepared taking into account the following requirements:

Electrical Library / www.elec.ru

the design depth of the blocks was maintained from the planning level; the correct laying and waterproofing of the joints of reinforced concrete blocks and pipes are ensured; ensured the cleanliness and alignment of the channels;

there are double covers (the lower one with a lock) of the manholes of the wells, metal ladders or brackets for lowering into the well.

2.23. When constructing ramps for laying cables on their supporting structures (columns) and on spans, the embedded elements provided for by the project must be made for installing cable rollers, bypass devices and other devices.

2.24. The general contractor must present for acceptance for installation the construction readiness in residential buildings - by section, in public buildings - by floor (or by premises).

Reinforced concrete, gypsum concrete, expanded clay concrete floor panels, internal wall panels and partitions, reinforced concrete columns and prefabricated crossbars must have channels (pipes) for laying wires, niches, nests with embedded parts for installing plug sockets, switches, bells and bell buttons in accordance with working drawings. Cross-sections of channels and monolithic non-metallic pipes should not differ by more than 15% from those indicated in the working drawings.

The displacement of nests and niches at the junctions of adjacent building structures should not be more than 40 mm.

2.25. In buildings and structures handed over for the installation of electrical equipment, the general contractor must fulfill the stipulated architectural and construction drawings of holes, grooves, niches and nests in foundations, walls, partitions, ceilings and coverings, necessary for the installation of electrical equipment and installation products, laying pipes for electrical wiring and electrical networks.

The indicated holes, grooves, niches and nests, which were not left in the building structures during their erection, are carried out by the general contractor in accordance with the architectural and construction drawings.

Holes with a diameter of less than 30 mm that cannot be taken into account in the development of drawings and which cannot be provided for in building structures according to the conditions of their manufacturing technology (holes in walls, partitions, ceilings only for installing dowels, pins and pins of various supporting and supporting structures) must carried out by the electrical installation organization at the place of work.

After completing the electrical work, the general contractor is obliged to seal the holes, grooves, niches and nests.

2.26. When accepting foundations for transformers, the presence and correctness of installation of anchors for fastening traction devices during rolling of transformers and foundations for jacks for turning rollers must be checked.

3. PRODUCTION OF ELECTRICAL WORKS GENERAL REQUIREMENTS

3.1. When loading, unloading, moving, lifting and installing electrical equipment, measures must be taken to protect it from damage, while heavy electrical equipment must be securely slinged to the parts provided for this purpose or in the places specified by the manufacturer.

3.2. Electrical equipment during installation is not subject to disassembly and revision, except in cases where it is provided by state and industry standards or technical conditions, agreed in accordance with the established procedure.

Disassembly of equipment received sealed from the manufacturer is prohibited.

3.3. Electrical equipment and cable products that are deformed or with damage to the protective coatings are not subject to installation until the damage and defects are eliminated in the prescribed manner.

3.4. In the production of electrical work, standard sets of special tools should be used for the types of electrical work, as well as mechanisms and devices designed for this purpose.

Electrical Library / www.elec.ru

3.5. As supporting structures and fasteners for the installation of trolleys, busbars, trays, boxes, hinged panels and control posts, of protective and starting equipment and lamps, factory-made products should be used that have increased assembly readiness (with a protective coating, adapted for fastening without welding and do not require large labor costs for machining).

Fastening of supporting structures should be carried out by welding to embedded parts provided in building elements, or by fasteners (dowels, pins, pins, etc.). The method of fastening must be indicated in the working drawings.

3.6. The color designation of current-carrying buses of switchgears, trolleys, grounding buses, overhead lines should be performed in accordance with the instructions given in the project.

3.7. During the performance of work, the electrical installation organization must comply with the requirements of GOST 12.1.004-76 and the Fire Safety Rules during construction and installation works. When the operational regime is introduced at the facility, ensuring fire safety is the responsibility of the customer.

CONTACT CONNECTIONS

3.8. Collapsible connections of tires and cores of wires and cables to the contact terminals of electrical equipment, installation products and bus ducts must meet the requirements of GOST 10434-82.

3.9. In the places where the conductors of wires and cables are connected, a supply of wire or cable should be provided to ensure the possibility of re-connection.

3.10. The joints and branches must be accessible for inspection and repair. The insulation of connections and branches should be equivalent to the insulation of the cores of the wires and cables to be connected.

At the points of connections and branches, wires and cables should not be subjected to mechanical stress.

3.11. The termination of the cable core with impregnated paper insulation should be performed with sealed current-carrying fittings (lugs), which do not allow the cable impregnating compound to leak out.

3.12. Busbar connections and branches should be made, as a rule, non-separable (by welding).

In places where collapsible joints are required, busbar connections should be made with bolts or pressure plates. The number of collapsible joints should be minimal.

3.13. Connections of wires of overhead lines with voltage up to 20 kV should be performed:

a) in the loops of the anchor-angle type supports: with clamps - anchor and branch wedge; connecting oval, mounted by the crimp method; looped dies, with the help of thermite cartridges, and wires of different brands and sections - with hardware pressed clamps;

b) in the spans: connecting oval clamps, mounted by twisting. Single-wire wires are allowed to be connected by twisting. Butt Welding Single Wire

no wires allowed.

3.14. The connection of overhead lines with a voltage higher than 20 kV must be performed: a) in the loops of anchor-angle type supports:

steel aluminum wires with a section of 240 sq. mm and above - with the help of thermite cartridges and pressure testing with the help of explosion energy;

steel-aluminum wires with a cross-section of 500 sq. mm and above - using crimp connectors; wires of different brands - with bolt clamps; wires made of aluminum alloy - with loop-type clamps or connectors

oval, crimp-mounted; b) in the spans:

steel-aluminum wires with a cross-section up to 185 sq. mm and steel ropes with a cross-section up to 50 sq. mm - oval connectors, mounted by twisting;

steel ropes with a cross section of 70-95 sq. mm with oval connectors, mounted by crimping or crimping with additional thermite welding of the ends;

steel-aluminum wires with a cross-section of 240-400 sq. mm with connecting clamps, mounted by continuous crimping and crimping using explosion energy;

Electrical Library / www.elec.ru

steel-aluminum wires with a cross section of 500 sq. mm and more - with connecting clamps, mounted by the method of continuous crimping.

3.15. The connection of copper and steel-copper ropes with a cross-section of 35-120 sq. Mm, as well as aluminum wires with a cross-section of 120-185 sq. Mm during the installation of contact networks should be performed with oval connectors, steel ropes - with clamps with a connecting strip between them. Steel-copper ropes with a cross section of 50-95 sq. Mm are allowed to be joined with wedge clamps with a connecting bar between them.

ELECTRICAL WIRING General requirements

3.16. The rules of this subsection apply to the installation of electrical wiring for power, lighting and secondary circuits with voltages up to 1000 V AC and DC, laid inside and outside buildings and structures with insulated installation wires of all sections and unarmored cables with rubber or plastic insulation with a cross section of up to 16 sq. mm.

3.17. Installation of control cables should be carried out taking into account the requirements of paragraphs. 3.56-3.106.

3.18. Passages of non-armored cables, protected and unprotected wires through fireproof walls (partitions) and interfloor ceilings must be made in pipe sections, or in boxes, or openings, and through combustible ones - in steel pipe sections.

Openings in walls and ceilings must have a frame that excludes their destruction during operation. In places where wires and cables pass through walls, ceilings or their exit to the outside, gaps between wires, cables and a pipe (box, opening) should be sealed with an easily removable mass from a non-combustible material.

Sealing should be done on each side of the pipe (duct, etc.).

In the case of open laying of non-metallic pipes, the sealing of the places of their passage through fire barriers should be made with non-combustible materials immediately after laying the cables or wires into the pipes.

Sealing the gaps between pipes (box, opening) and the building structure (see clause 2.25), as well as between wires and cables laid in pipes (boxes, openings), with an easily removable mass from a non-combustible material should provide fire resistance corresponding to the fire resistance of the building structure ...

Laying wires and cables on trays and boxes

3.19. The design and degree of protection of trays and boxes, as well as the method of laying wires and cables on trays and in boxes (in bulk, bundles, multilayer, etc.) must be specified in the project.

3.20. The way the boxes are installed should not allow moisture to accumulate in them. The boxes used for open electrical wiring should have, as a rule, removable or opening covers.

3.21. For hidden gaskets, blind ducts should be used.

3.22. Wires and cables laid in boxes and on trays must be marked at the beginning and at the end of trays and boxes, as well as at the points of their connection to electrical equipment, and cables, in addition, also on the turns of the track and on branches.

3.23. Fasteners of unprotected wires and cables with a metal sheath with metal brackets or bands must be made with gaskets made of elastic insulating materials.

Laying wires on insulating supports

3.24. When laying on insulating supports, the connection or branching of the wires should be carried out directly at the insulator, clip, roller or on them.

3.25. The distances between the attachment points along the route and between the axes of parallel laid unprotected insulated wires on insulating supports should be indicated in the project.

Electrical Library / www.elec.ru

3.26. Hooks and brackets with insulators should be fixed only in the main material of the walls, and rollers and clamps for wires with a cross section of up to 4 mm2 incl. can be fixed to plaster or cladding of wooden buildings. Hook insulators must be securely fastened.

3.27. When fastening the rollers with wood grouses, metal and elastic washers should be placed under the heads of the wood grouses, and when fastening the rollers on metal, elastic washers should be placed under their bases.

Laying wires and cables on a steel rope

3.28. Wires and cables (in polyvinyl chloride, nitrite, lead or aluminum sheaths with rubber or polyvinyl chloride insulation) must be fixed to the supporting steel rope or to the wire with bandages or clamps installed at distances of no more than 0.5 m from each other.

3.29. Cables and wires laid on the ropes, at the points of their transition from the rope to the structures of buildings, must be unloaded from mechanical forces.

Vertical suspensions of the wiring on a steel rope should be located, as a rule, in the places where branch boxes, plug connectors, lamps, etc. are installed. The sag arrow of the rope in the spans between the fasteners should be within 1/40 - 1/60 of the span length. Splicing of ropes in the span between end fixtures is not allowed.

3.30. Guy braces should be installed on the wire rope to prevent the lighting wiring from swaying. The number of stretch marks should be determined in the working drawings.

3.31. For branches from special cable wires, special boxes must be used to create a cable loop, as well as a supply of cores necessary to connect an outgoing line using branch clamps without cutting the line.

Laying installation wires on building foundations

and inside the main building structures

3.32. Open and hidden laying of installation wires is not allowed at temperatures below minus 15 ° C.

3.33. In case of hidden laying of wires under a layer of plaster or in thin-walled (up to 80 mm) partitions, wires must be laid in parallel architectural and construction lines. The distance of horizontally laid wires from floor slabs should not exceed 150 mm.

V building structures with a thickness of more than 80 mm, wires should be laid along the shortest routes.

3.34. All connections and branches of the installation wires must be made by welding, crimping in sleeves or using clamps in branch boxes.

Metal junction boxes in the places where wires are inserted into them must have bushings made of insulating materials. It is allowed to use pieces of PVC tube instead of bushings. In dry rooms, it is allowed to place branches of wires in the nests and niches of walls and floors, as well as in the voids of the floors. The walls of the nests and niches should be smooth, the branches of the wires located in the nests and niches should be covered with covers made of non-combustible material.

3.35. Fastening of flat wires with hidden laying should ensure their snug fit to the building foundations. In this case, the distances between the attachment points should be:

a) when laying on horizontal and vertical sections of plastering wire bundles - no more than 0.5 m; single wires -0.9 m;

b) when covering wires with dry plaster - up to 1.2 m.

3.36. The plinth wiring device must provide separate routing of power and low-current wires.

3.37. The fixing of the plinth should ensure its tight fit to the building bases, while the pull-off force should be at least 190 N, and the gap between the plinth, wall and floor should be no more than 2 mm. Skirting boards should be made of non-combustible and non-combustible materials with electrical insulating properties.

Electrical Library / www.elec.ru

3.38. In accordance with GOST 12504-80, GOST 12767-80 and GOST 9574-80 in the panels must be provided with internal channels or embedded plastic pipes and embedded elements for hidden replaceable electrical wiring, sockets and holes for installing junction boxes, switches and sockets.

Holes for wiring accessories and broaching niches in wall panels adjacent apartments should not be cross-cutting. If, according to the conditions of the manufacturing technology, it is not possible to make holes blind, then sound-insulating gaskets made of vinyl foam or other non-combustible sound-insulating material must be laid in them.

3.39. The installation of pipes and boxes in reinforcing cages should be carried out on the conductors according to the working drawings that determine the attachment points for the installation, branch and ceiling boxes. To ensure that the boxes are positioned flush with the surface of the panels after molding, they should be fixed to the reinforcing cage in such a way that when the boxes are installed in blocks, the height of the block corresponds to the thickness of the panel, and when the boxes are installed separately to prevent their displacement inside the panels, the front surface of the boxes should protrude beyond the plane of the reinforcing cage. on the 30-35 mm.

3.40. The channels should have a smooth surface along their entire length, without sagging and sharp corners. The thickness of the protective layer above the channel (pipe) must be at least 10 mm.

The length of channels between broaching niches or boxes should be no more than 8 m.

Laying wires and cables in steel pipes

3.41. Steel pipes are allowed to be used for electrical wiring only in cases specially justified in the project in accordance with the requirements of regulatory documents approved in the manner established by SNiP 1.01.01-82.

3.42. Steel pipes used for electrical wiring must have an inner surface that excludes damage to the insulation of the wires when they are pulled into the pipe and an anti-corrosion coating of the outer surface. For pipes embedded in building structures, an external anti-corrosion coating is not required. Pipes laid in rooms with a chemically active environment, inside and outside, must have an anti-corrosion coating that is resistant to the conditions of this environment. In places where wires exit from steel pipes, insulating sleeves should be installed.

3.43. Steel pipes for electrical wiring, laid in the foundations for technological equipment, must be fixed to supporting structures or to reinforcement before concreting the foundations. In places where pipes exit from the foundation into the ground, the measures provided for in the working drawings must be carried out against the shearing of the pipes in case of sedimentation of the ground or foundation.

3.44. In the places where the pipes intersect the expansion and sedimentary joints, compensating devices must be made in accordance with the instructions in the working drawings.

3.45. The distances between the attachment points of openly laid steel pipes should not exceed the values ​​indicated in table. 1. Fastening steel wiring pipes directly

To technological pipelines, as well as their welding directly to various structures are not allowed.

Table 1

The greatest

The greatest

Conditional

admissible

Conditional

admissible

pipe passage,

distance

pipe passage, mm

distance

between points

between points

fastening, m

fastening, m

Electrical Library / www.elec.ru

3.46. When bending pipes, as a rule, normalized angles of rotation of 90, 120 should be used.

and 135 ° and normalized bending radii of 400, 800 and 1000 mm. A bending radius of 400 mm should be used for pipes laid in ceilings and for vertical outlets; 800 and 1000 mm - when laying pipes in monolithic foundations and when laying cables with single-wire conductors in them. When preparing packages and blocks of pipes, you should also adhere to the specified normalized angles and bending radii.

3.47. When laying wires in vertically laid pipes (risers), their fastening should be provided, and the fastening points should be spaced from each other at a distance not exceeding, m:

for wires up to 50 sq. mm incl. ................... thirty

the same, from 70 to 150 sq. mm incl. .................. twenty

" "185" 240 sq. Mm "....................... 15

Fastening of wires should be carried out using clamps or clamps in broaching or branch boxes or at the ends of pipes.

3.48. Pipes with hidden laying in the floor must be buried at least 20 mm and protected with a layer of cement mortar. It is allowed to install branch and pull-out boxes in the floor, for example, for modular wiring.

3.49. Distances between broaching boxes (boxes) should not exceed, m: on straight sections 75, with one pipe bend - 50, with two - 40, with three-20.

Wires and cables in pipes must lie freely, without tension. The diameter of the pipes should be taken in accordance with the instructions in the working drawings.

Laying wires and cables in non-metallic pipes

3.50. The laying of non-metallic (plastic) pipes for tightening wires and cables in them must be carried out in accordance with the working drawings at an air temperature of at least minus 20 and no higher than plus 60 ° C.

V on foundations, plastic pipes (usually polyethylene) should be laid only on horizontally compacted soil or a layer of concrete.

V foundations up to 2 m deep, PVC pipes can be laid. In this case, measures must be taken against mechanical damage during concreting and backfilling of soil.

3.51. The fastening of openly laid non-metallic pipes must allow their free movement (movable fastening) during linear expansion or contraction from changes in the ambient temperature. The distances between the points of installation of movable mounts must correspond to those indicated in table. 2.

table 2

Distances

Distances

Outer

between points

Outer

between points

pipe diameter,

fastening at

pipe diameter,

fastening at

horizontal and

horizontal

vertical

and vertical

gasket, mm

gasket, mm

3.52. The thickness of the concrete solution above the pipes (single and blocks) when they are embedded

v floor preparations should be at least 20 mm. At the intersection of pipe routes, a protective layer of concrete mortar between the pipes is not required. In this case, the depth of the top row must comply with the above requirements. If when crossing pipes it is impossible

Electrical Library / www.elec.ru

SNiP 3.05.06-85

BUILDING REGULATIONS

Electrical devices

Date of introduction 1986-01-07

DEVELOPED by VNIIproektelektromontazh by the USSR Ministry of Montazhspetsstroy (V.K. Dobrynin, I.N. Dolgov - leaders

topics, Candidate of Engineering Sciences V.A. Antonov, A.L. Blinchikov, V.V. Belotserkovets, V.A. Demyantsev, Candidate of Technical Sciences N.I. Korotkov, E.A. technical sciences Yu.A. Roslov, S.N. Starostin, A.K. Shulzhitskiy), Orgenergostroy of the USSR Ministry of Energy (G.N. Elenbogen, N.V. Belanov, N.A. Voinilovich, A.L. Gonchar, N.M. Lerner), Sellenergoproekt of the USSR Ministry of Energy (G.F. Sumin, Yu.V. Nepomnyashchy), UGPI Tyazhpromelektroproekt Minmontazhspetsstroy of the Ukrainian SSR (E.G. Poddubny, A.A. Koba).

INTRODUCED by the USSR Ministry of Montazhspetsstroy.

APPROVED by the decree of the USSR State Committee for Construction of December 11, 1985 No. 215

REPLACE SNiP III-33-76 *, SN 85-74, SN 102-76 *.

These rules apply to the production of work during the construction of new, as well as during the reconstruction, expansion and technical re-equipment of existing enterprises for the installation and commissioning of electrical devices, including: electrical substations, distribution points and overhead power lines with a voltage of up to 750 kV, cable lines with a voltage of up to 220 kV, relay protection, power electrical equipment, indoor and outdoor electrical lighting, grounding devices.

The rules do not apply to. production and acceptance of works on the installation and commissioning of electrical devices of the subway, mines and mines, contact networks of electrified transport, signaling systems for railway transport, as well as rooms with a strict regime of nuclear power plants, which must be carried out in accordance with departmental building codes approved in the manner prescribed by SNiP 1.01.01-82.

The rules must be observed by all organizations and enterprises involved in the design and construction of new, expansion, reconstruction and technical re-equipment of existing enterprises.

1. GENERAL PROVISIONS

1.1. When organizing and performing work on the installation and commissioning of electrical devices, the requirements of SNiP 3.01.01-85, SNiP III-4-80, state standards, technical conditions should be observed. Of the Rules for the Installation of Electrical Installations, approved by the USSR Ministry of Energy, and departmental regulatory documents approved in the manner established by SNiP 1.01.01-82.

1.2. Installation and commissioning of electrical devices should be carried out in accordance with the working drawings of the main sets of drawings of electrical brands; on working documentation for electric drives; according to the working documentation for non-standardized equipment, prepared by the design organization; according to the working documentation of enterprises - manufacturers of technological equipment, supplying power and control cabinets with it.

1.3. The installation of electrical devices should be carried out on the basis of the use of nodal and complete-block construction methods, with the installation of equipment supplied by enlarged units that do not require straightening, cutting, drilling or other adjusting operations and adjustments during installation. When accepting the working documentation for the production of work, it is necessary to check that it takes into account the requirements for the industrialization of the installation of electrical devices, as well as the mechanization of work on laying cables, rigging and installing technological equipment.

1.4. Electrical work should be performed, as a rule, in two stages.

In the first stage, inside buildings and structures, work is carried out on the installation of support structures for the installation of electrical equipment and busbars, for laying cables and wires, installing trolleys for electric bridge cranes, installing steel and plastic pipes for electrical wiring, laying hidden wiring wires before plastering and finishing works, as well as work on the installation of external cable networks and grounding networks. The work of the first stage should be carried out in buildings and structures according to a combined schedule simultaneously with the main construction work, while measures should be taken to protect the installed structures and laid pipes from breakdowns and contamination.

In the second stage, work is performed on the installation of electrical equipment, laying cables and wires, busbars and connecting cables and wires to the terminals of electrical equipment. In the electrical rooms of the objects of the second stage, work should be carried out after the completion of the complex of general construction and finishing works and after the completion of the installation of plumbing devices, and in other rooms and zones - after the installation of technological equipment, electric motors and other electrical receivers, installation of technological, sanitary-technical pipelines and ventilation ducts.

At small objects remote from the locations of electrical installation organizations, work should be carried out by field complex teams with the combination of two stages of their implementation in one.

1.5. Electrical equipment, products and materials should be supplied according to a schedule agreed with the electrical installation organization, which should provide for the priority delivery of materials and products included in the specifications for blocks to be manufactured at the assembly and packaging enterprises of electrical installation organizations.

1.6. The completion of the installation of electrical devices is the completion of individual tests of the mounted electrical equipment and the signing by the working commission of an act of acceptance of electrical equipment after an individual test. The beginning of individual tests of electrical equipment is the moment of introduction of an operating mode at a given electrical installation, announced by the customer on the basis of a notice from the commissioning and electrical installation organizations.

1.7. At each construction site, during the installation of electrical devices, special journals of electrical installation work should be kept in accordance with SNiP 3.01.01-85, and upon completion of the work, the electrical installation organization is obliged to transfer to the general contractor the documentation presented by the working commission in accordance with SNiP III-3-81. The list of acts and protocols of inspections and tests is determined by the VSN, approved in accordance with the procedure established by SNiP 1.01.01-82.

2. PREPARATION FOR PRODUCTION

ELECTRICAL WORKS

2.1. The installation of electrical devices must be preceded by preparation in accordance with SNiP 3.01.01-85 and these rules.

2.2. Prior to the commencement of work at the facility, the following activities must be performed:

a) the working documentation was received in the quantity and within the timeframe determined by the Rules on Contracts for Capital Construction, approved by the resolution of the Council of Ministers of the USSR, and the Regulation on the relationship of organizations, general contractors with subcontractors, approved by the USSR State Construction Committee and the USSR State Planning Committee;

b) the schedules for the supply of equipment, products and materials were agreed, taking into account the technological sequence of work, the list of electrical equipment installed with the involvement of the chief installation personnel of the supplier enterprises, the conditions for transporting heavy and large-sized electrical equipment to the installation site;

c) the necessary premises have been taken to accommodate teams of workers, engineering and technical workers, a production base, as well as for storing materials and tools with the provision of measures for labor protection, fire safety and environmental protection in accordance with SNiP 3.01.01-85;

d) a project for the production of works has been developed, the engineering and technical workers and foremen have been familiarized with the working documentation and estimates, organizational and technical solutions for the project for the production of works;

e) the acceptance of the construction part of the object for the installation of electrical devices in accordance with the requirements of these rules has been carried out and the measures for labor protection, fire safety and environmental protection during the work are carried out as provided for by the rules and regulations;

f) performed by the general contractor general construction and auxiliary works stipulated by the Regulations on the relationship of organizations - general contractors with subcontractors.

2.3. Equipment, products, materials and technical documentation must be transferred for installation in accordance with the Rules on Contracts for Capital Construction and the Regulations on the Relationship of Organizations - General Contractors with Subcontractors.

2.4. When the equipment is accepted for installation, it is inspected, the completeness is checked (without disassembly), the availability and validity of the manufacturer's warranties are checked.

2.5. The condition of the cables on the drums should be checked in the presence of the customer by means of an external examination. The results of the inspection are documented in an act.

2.6. When accepting prefabricated reinforced concrete structures of overhead lines (OHL), the following should be checked:

the dimensions of the elements, the position of the steel embedded parts, as well as the quality of the surfaces and the appearance of the elements. The specified parameters must comply with GOST 13015.0-83, GOST 22687.0-85, GOST 24762-81, GOST 26071-84, GOST 23613-79, as well as PUE;

the presence on the surface of reinforced concrete structures intended for installation in an aggressive environment, waterproofing made at the manufacturer.

2.7. Insulators and line fittings must meet the requirements of the relevant state standards and specifications. When accepting them, you should check:

availability of a manufacturer's passport for each batch of insulators and linear fittings, certifying their quality;

the absence of cracks, deformations, cavities, chips, damage to the glaze on the surface of the insulators, as well as swaying and turning of the steel reinforcement relative to the cement embedding or porcelain;

the absence of cracks, deformations, cavities and damage to galvanized steel and threads in linear reinforcement.

It is allowed to paint over minor damages of galvanized steel.

2.8. Elimination of defects and damages discovered during the transfer of electrical equipment is carried out in accordance with the Rules on Contracts for Capital Construction.

2.9. Electrical equipment, for which the standard storage period specified in state standards or technical conditions has expired, is accepted for installation only after a pre-installation audit, correction of defects and tests. The results of the work carried out must be entered in the forms, passports and other accompanying documentation, or an act of carrying out the indicated work must be drawn up.

2.10. Electrical equipment, products and materials accepted for installation should be stored in accordance with the requirements of state standards or technical specifications.

2.11. For large and complex objects with a large volume of cable lines in tunnels, canals and cable half-floors, as well as electrical equipment in electrical rooms, the construction organization design should define measures for advanced installation (against the installation of cable networks) of internal fire-fighting water supply systems, automatic fire extinguishing and automatic fire extinguishing systems. alarms provided by the working drawings.

2.12. In electrical rooms (switchboards, control rooms, substations and switchgears, machine rooms, battery rooms, cable tunnels and channels, cable half-floors, etc.), clean floors with drainage channels, the necessary slope and waterproofing and finishing works (plastering and painting ), embedded parts were installed and installation openings were left, the lifting and handling mechanisms and devices provided for by the project were mounted, pipe blocks, holes and openings for the passage of pipes and cables, grooves, niches and nests were prepared in accordance with the architectural and construction drawings and the work production project, power supply for temporary electric lighting in all rooms is made.

2.13. In buildings and structures, heating and ventilation systems must be put into operation, bridges, platforms and structures of suspended ceilings provided by the project for the installation and maintenance of electric lighting installations located at a height, as well as fixing structures for multi-lamp lamps (chandeliers) weighing over 100 kg; laid outside and inside buildings and structures asbestos-cement pipes and pipes and pipe blocks for the passage of cables provided for by the working construction drawings.

2.14. Foundations for electrical machines should be handed over for installation with fully completed construction and finishing works, installed air coolers and ventilation ducts, with benchmarks and axial strips (measurements) in accordance with the requirements of SNiP 3.02.01-83 and these rules.

2.15. On the supporting (rough) surfaces of foundations, depressions of no more than 10 mm and slopes up to 1: 100 are allowed. Deviations in building dimensions should be no more than: in terms of axial dimensions in the plan - plus 30 mm, in elevation marks of the surface of the foundations (excluding the height of the grout) - minus 30 mm, in terms of the dimensions of the ledges in the plan - minus 20 mm, in terms of the dimensions of wells - plus 20 mm, along the marks of the ledges in the recesses and wells - minus 20 mm, along the axes of the anchor bolts in the plan - ± 5 mm, along the axes of the embedded anchor devices in the plan - ± 10 mm, along the marks of the upper ends of the anchor bolts - ± 20 mm.

2.16. Delivery and acceptance of foundations for the installation of electrical equipment, the installation of which is carried out with the involvement of the installation supervision personnel, is carried out jointly with representatives of the organization that carries out installation supervision.

2.17. At the end of the finishing work in the battery rooms, acid- or alkali-resistant coatings of walls, ceilings and floors must be made, heating, ventilation, water supply and sewerage systems must be installed and tested.

2.18. Before the start of electrical work on open switchgears with a voltage of 35 kV and above, the construction organization must complete the construction of access roads, approaches and entrances, install bus and linear portals, build foundations for electrical equipment, cable channels with ceilings, fences around the switchgear, emergency discharge tanks oils, underground utilities and the planning of the territory is completed. In the structures of portals and foundations for the equipment, the embedded parts and fasteners provided for by the project must be installed, which are necessary for fastening the garlands of insulators and equipment. In cable ducts and tunnels, embedded parts must be installed for fastening cable structures and air ducts. The construction of a water supply system and other fire-prevention devices provided for by the project must also be completed.

2.19. The construction part of the outdoor switchgear and substations with a voltage of 330-750 kV should be accepted for installation for their full development, provided for by the project for the billing period.

2.20. Before the start of electrical work on the construction of overhead power lines with voltages up to 1000 V and above, preparatory work must be performed in accordance with SNiP 3.01.01-85, including:

Inventory structures were prepared at the locations of foreman's plots and temporary bases for storing materials and equipment; temporary access roads, bridges and assembly sites were built;

glades are arranged;

the demolition of buildings envisaged by the project and the reconstruction of intersected engineering structures located on or near the overhead line route and hindering the production of work were carried out.

2.21. The routes for laying the cable in the ground must be prepared for the beginning of its laying in the following volume: water is pumped out of the trench and stones, clods of earth, construction waste are removed; at the bottom of the trench there is a cushion of loosened earth; punctures were made in the ground at the intersection of the route with roads and other engineering structures, pipes were laid.

After laying the cables in the trench and the submission by the electrical installation organization of the act for the hidden work on laying the cables, the trench should be filled up.

2.22. Block sewerage routes for cable laying must be prepared taking into account the following requirements:

the design depth of the blocks was maintained from the planning level;

the correct laying and waterproofing of the joints of reinforced concrete blocks and pipes are ensured;

ensured the cleanliness and alignment of the channels;

there are double covers (the lower one with a lock) of the manholes of the wells, metal ladders or brackets for lowering into the well.

2.23. When constructing ramps for laying cables on their supporting structures (columns) and on spans, the embedded elements provided for by the project must be made for installing cable rollers, bypass devices and other devices.

2.24. The general contractor must present for acceptance for installation the construction readiness in residential buildings - by section, in public buildings - by floor (or by premises).

Reinforced concrete, gypsum concrete, expanded clay concrete floor panels, internal wall panels and partitions, reinforced concrete columns and prefabricated crossbars must have channels (pipes) for laying wires, niches, nests with embedded parts for installing plug sockets, switches, bells and bell buttons in accordance with working drawings. Cross-sections of channels and monolithic non-metallic pipes should not differ by more than 15% from those indicated in the working drawings.

The displacement of nests and niches at the junctions of adjacent building structures should not be more than 40 mm.

2.25. In buildings and structures handed over for the installation of electrical equipment, the general contractor must make holes, grooves, niches and nests in the foundations, walls, partitions, ceilings and coatings provided for by the architectural and construction drawings, which are necessary for the installation of electrical equipment and installation products, laying pipes for electrical wiring and electrical networks.

The indicated holes, grooves, niches and nests, which were not left in the building structures during their erection, are carried out by the general contractor in accordance with the architectural and construction drawings.

Holes with a diameter of less than 30 mm that cannot be taken into account in the development of drawings and which cannot be provided for in building structures according to the conditions of their manufacturing technology (holes in walls, partitions, ceilings only for installing dowels, pins and pins of various supporting and supporting structures) must carried out by the electrical installation organization at the place of work.

After completing the electrical work, the general contractor is obliged to seal the holes, grooves, niches and nests.

2.26. When accepting foundations for transformers, the presence and correctness of installation of anchors for fastening traction devices during rolling of transformers and foundations for jacks for turning rollers must be checked.

3. PRODUCTION OF ELECTRICAL INSTALLATION WORKS

GENERAL REQUIREMENTS

3.1. When loading, unloading, moving, lifting and installing electrical equipment, measures must be taken to protect it from damage, while heavy electrical equipment must be securely slinged to the parts provided for this purpose or in the places specified by the manufacturer.

3.2. Electrical equipment during installation is not subject to disassembly and revision, except for cases when it is provided for by state and industry standards or technical conditions agreed in the prescribed manner.

Disassembly of equipment received sealed from the manufacturer is prohibited.

3.3. Electrical equipment and cable products that are deformed or with damage to the protective coatings are not subject to installation until the damage and defects are eliminated in the prescribed manner.

3.4. In the production of electrical work, standard sets of special tools should be used for the types of electrical work, as well as mechanisms and devices designed for this purpose.

3.5. As supporting structures and fasteners for the installation of trolleys, bus ducts, trays, boxes, hinged shields and control posts, protective and starting equipment and lamps, factory-made products should be used that have increased assembly readiness (with a protective coating, adapted for fastening without welding and not requiring large labor costs for machining).

Fastening of supporting structures should be carried out by welding to embedded parts provided in building elements, or by fasteners (dowels, pins, pins, etc.). The method of fastening must be indicated in the working drawings.

3.6. The color designation of current-carrying buses of switchgears, trolleys, grounding buses, overhead lines should be performed in accordance with the instructions given in the project.

3.7. During the performance of work, the electrical installation organization must comply with the requirements of GOST 12.1.004-76 and the Fire Safety Rules in the performance of construction and installation works. When the operational regime is introduced at the facility, ensuring fire safety is the responsibility of the customer.

CONTACT CONNECTIONS

3.8. Collapsible connections of buses and cores of wires and cables to contact terminals of electrical equipment, installation products and bus ducts must meet the requirements of GOST 10434-82.

3.9. In the places where the conductors of wires and cables are connected, a supply of wire or cable should be provided to ensure the possibility of re-connection.

3.10. The joints and branches must be accessible for inspection and repair. The insulation of connections and branches should be equivalent to the insulation of the cores of the wires and cables to be connected.

At the points of connections and branches, wires and cables should not be subjected to mechanical stress.

3.11. The termination of the cable core with impregnated paper insulation should be performed with sealed current-carrying fittings (lugs), which do not allow the cable impregnating compound to leak out.

3.12. Busbar connections and branches should be made, as a rule, non-separable (by welding).

In places where collapsible joints are required, busbar connections should be made with bolts or pressure plates. The number of collapsible joints should be minimal.

3.13. Connections of wires of overhead lines with voltage up to 20 kV should be performed:

a) in the loops of the anchor-angle type supports: with clamps - anchor and branch wedge; connecting oval, mounted by the crimp method; looped dies, with the help of thermite cartridges, and wires of different brands and sections - with hardware pressed clamps;

b) in the spans: connecting oval clamps, mounted by twisting.

Single-wire wires are allowed to be connected by twisting. Butt welding of solid wires is not allowed.

3.14. The connection of overhead lines with a voltage higher than 20 kV must be performed:

a) in the loops of the anchor-angle type supports:

steel-aluminum wires with a cross-section of 240 sq. mm and above - with the help of thermite cartridges and crimping with the help of explosion energy;

steel-aluminum wires with a cross-section of 500 sq. mm and above - using crimp connectors;

wires of different brands - with bolt clamps;

wires made of aluminum alloy - with loop-type clamps or oval connectors, mounted by the crimping method;

b) in the spans:

steel-aluminum wires with a cross-section up to 185 sq. mm and steel ropes with a cross-section up to 50 sq. mm - oval connectors, mounted by twisting;

steel ropes with a cross section of 70-95 sq. mm with oval connectors, mounted by crimping or crimping with additional thermite welding of the ends;

steel-aluminum wires with a cross-section of 240-400 sq. mm with connecting clamps, mounted by continuous crimping and crimping using explosion energy;

steel-aluminum wires with a cross section of 500 sq. mm and more - with connecting clamps, mounted by the method of continuous crimping.

3.15. The connection of copper and steel-copper ropes with a cross-section of 35-120 sq. Mm, as well as aluminum wires with a cross-section of 120-185 sq. Mm during the installation of contact networks should be performed with oval connectors, steel ropes - with clamps with a connecting strip between them. Steel-copper ropes with a cross section of 50-95 sq. Mm are allowed to be joined with wedge clamps with a connecting bar between them.

ELECTRICAL WIRING

General requirements

3.16. The rules of this subsection apply to the installation of electrical wiring for power, lighting and secondary circuits with voltages up to 1000 V AC and DC, laid inside and outside buildings and structures with insulated installation wires of all sections and unarmored cables with rubber or plastic insulation with a cross section of up to 16 sq. mm.

3.17. Installation of control cables should be carried out taking into account the requirements of paragraphs. 3.56-3.106.

3.18. Passages of non-armored cables, protected and unprotected wires through fireproof walls (partitions) and interfloor ceilings must be made in pipe sections, or in boxes, or openings, and through combustible ones - in steel pipe sections.

Openings in walls and ceilings must have a frame that excludes their destruction during operation. In places where wires and cables pass through walls, ceilings or their exit to the outside, gaps between wires, cables and a pipe (box, opening) should be sealed with an easily removable mass from a non-combustible material.

Sealing should be done on each side of the pipe (duct, etc.).

In the case of open laying of non-metallic pipes, the sealing of the places of their passage through fire barriers should be made with non-combustible materials immediately after laying the cables or wires into the pipes.

Sealing the gaps between pipes (box, opening) and the building structure (see clause 2.25), as well as between wires and cables laid in pipes (boxes, openings), with an easily removable mass from a non-combustible material should provide fire resistance corresponding to the fire resistance of the building structure ...

Laying wires and cables on trays and boxes

3.19. The design and degree of protection of trays and boxes, as well as the method of laying wires and cables on trays and in boxes (in bulk, bundles, multilayer, etc.) must be specified in the project.

3.20. The way the boxes are installed should not allow moisture to accumulate in them. The boxes used for open electrical wiring should have, as a rule, removable or opening covers.

3.21. For hidden gaskets, blind ducts should be used.

3.22. Wires and cables laid in boxes and on trays must be marked at the beginning and at the end of trays and boxes, as well as at the points of their connection to electrical equipment, and cables, in addition, also on the turns of the track and on branches.

3.23. Fasteners of unprotected wires and cables with a metal sheath with metal brackets or bands must be made with gaskets made of elastic insulating materials.

Laying wires on insulating supports

3.24. When laying on insulating supports, the connection or branching of the wires should be carried out directly at the insulator, clip, roller or on them.

3.25. The distances between the attachment points along the route and between the axes of parallel laid unprotected insulated wires on insulating supports should be indicated in the project.

3.26. Hooks and brackets with insulators should be fixed only in the main material of the walls, and rollers and clamps for wires with a cross section of up to 4 mm2 incl. can be fixed to plaster or cladding of wooden buildings. Hook insulators must be securely fastened.

3.27. When fastening the rollers with wood grouses, metal and elastic washers should be placed under the heads of the wood grouses, and when fastening the rollers on metal, elastic washers should be placed under their bases.

Laying wires and cables on a steel rope

3.28. Wires and cables (in polyvinyl chloride, nitrite, lead or aluminum sheaths with rubber or polyvinyl chloride insulation) must be fixed to the supporting steel rope or to the wire with bandages or clamps installed at distances of no more than 0.5 m from each other.

3.29. Cables and wires laid on the ropes, at the points of their transition from the rope to the structures of buildings, must be unloaded from mechanical forces.

Vertical suspensions of the wiring on a steel rope should be located, as a rule, in the places where branch boxes, plug connectors, lamps, etc. are installed. The sag arrow of the rope in the spans between the fasteners should be within 1/40 - 1/60 of the span length. Splicing of ropes in the span between end fixtures is not allowed.

3.30. Guy braces should be installed on the wire rope to prevent the lighting wiring from swaying. The number of stretch marks should be determined in the working drawings.

3.31. For branches from special cable wires, special boxes must be used to create a cable loop, as well as a supply of cores necessary to connect an outgoing line using branch clamps without cutting the line.

Laying installation wires on building foundations

and inside the main building structures

3.32. Open and hidden laying of installation wires is not allowed at temperatures below minus 15 ° C.

3.33. With hidden laying of wires under a layer of plaster or in thin-walled (up to 80 mm) partitions, wires should be laid parallel to the architectural and construction lines. The distance of horizontally laid wires from floor slabs should not exceed 150 mm. In building structures with a thickness of more than 80 mm, wires must be laid along the shortest routes.

3.34. All connections and branches of the installation wires must be made by welding, crimping in sleeves or using clamps in branch boxes.

Metal junction boxes in the places where wires are inserted into them must have bushings made of insulating materials. It is allowed to use pieces of PVC tube instead of bushings. In dry rooms, it is allowed to place branches of wires in the nests and niches of walls and floors, as well as in the voids of the floors. The walls of the nests and niches should be smooth, the branches of the wires located in the nests and niches should be covered with covers made of non-combustible material.

3.35. Fastening of flat wires with hidden laying should ensure their snug fit to the building foundations. In this case, the distances between the attachment points should be:

a) when laying on horizontal and vertical sections of plastering wire bundles - no more than 0.5 m; single wires -0.9 m;

b) when covering wires with dry plaster - up to 1.2 m.

SNiP 3.05.06-85

BUILDING REGULATIONS

Electrical devices

Date of introduction 1986-01-07

DEVELOPED by VNIIproektelektromontazh by the USSR Ministry of Montazhspetsstroy (V.K. Dobrynin, I.N. Dolgov - leaders

topics, Candidate of Engineering Sciences V.A. Antonov, A.L. Blinchikov, V.V. Belotserkovets, V.A. Demyantsev, Candidate of Technical Sciences N.I. Korotkov, E.A. technical sciences Yu.A. Roslov, S.N. Starostin, A.K. Shulzhitskiy), Orgenergostroy of the USSR Ministry of Energy (G.N. Elenbogen, N.V. Belanov, N.A. Voinilovich, A.L. Gonchar, N.M. Lerner), Sellenergoproekt of the USSR Ministry of Energy (G.F. Sumin, Yu.V. Nepomnyashchy), UGPI Tyazhpromelektroproekt Minmontazhspetsstroy of the Ukrainian SSR (E.G. Poddubny, A.A. Koba).

INTRODUCED by the USSR Ministry of Montazhspetsstroy.

APPROVED by the decree of the USSR State Committee for Construction of December 11, 1985 No. 215

REPLACE SNiP III-33-76 *, SN 85-74, SN 102-76 *.

These rules apply to the production of work during the construction of new, as well as during the reconstruction, expansion and technical re-equipment of existing enterprises for the installation and commissioning of electrical devices, including: electrical substations, distribution points and overhead power lines with a voltage of up to 750 kV, cable lines with a voltage of up to 220 kV, relay protection, power electrical equipment, indoor and outdoor electrical lighting, grounding devices.

The rules do not apply to. production and acceptance of works on the installation and commissioning of electrical devices of the subway, mines and mines, contact networks of electrified transport, signaling systems for railway transport, as well as rooms with a strict regime of nuclear power plants, which must be carried out in accordance with departmental building codes approved in the manner prescribed by SNiP 1.01.01-82.

The rules must be observed by all organizations and enterprises involved in the design and construction of new, expansion, reconstruction and technical re-equipment of existing enterprises.

1. GENERAL PROVISIONS

1.1. When organizing and performing work on the installation and commissioning of electrical devices, the requirements of SNiP 3.01.01-85, SNiP III-4-80, state standards, technical conditions should be observed. Of the Rules for the Installation of Electrical Installations, approved by the USSR Ministry of Energy, and departmental regulatory documents approved in the manner established by SNiP 1.01.01-82.

1.2. Installation and commissioning of electrical devices should be carried out in accordance with the working drawings of the main sets of drawings of electrical brands; on working documentation for electric drives; according to the working documentation for non-standardized equipment, prepared by the design organization; according to the working documentation of enterprises - manufacturers of technological equipment, supplying power and control cabinets with it.

1.3. The installation of electrical devices should be carried out on the basis of the use of nodal and complete-block construction methods, with the installation of equipment supplied by enlarged units that do not require straightening, cutting, drilling or other adjusting operations and adjustments during installation. When accepting the working documentation for the production of work, it is necessary to check that it takes into account the requirements for the industrialization of the installation of electrical devices, as well as the mechanization of work on laying cables, rigging and installing technological equipment.

1.4. Electrical work should be performed, as a rule, in two stages.

In the first stage, inside buildings and structures, work is carried out on the installation of support structures for the installation of electrical equipment and busbars, for laying cables and wires, installing trolleys for electric bridge cranes, installing steel and plastic pipes for electrical wiring, laying hidden wiring wires before plastering and finishing works, as well as work on the installation of external cable networks and grounding networks. The work of the first stage should be carried out in buildings and structures according to a combined schedule simultaneously with the main construction work, while measures should be taken to protect the installed structures and laid pipes from breakdowns and contamination.

In the second stage, work is performed on the installation of electrical equipment, laying cables and wires, busbars and connecting cables and wires to the terminals of electrical equipment. In the electrical rooms of the objects of the second stage, work should be carried out after the completion of the complex of general construction and finishing works and after the completion of the installation of plumbing devices, and in other rooms and zones - after the installation of technological equipment, electric motors and other electrical receivers, installation of technological, sanitary-technical pipelines and ventilation ducts.

At small objects remote from the locations of electrical installation organizations, work should be carried out by field complex teams with the combination of two stages of their implementation in one.

1.5. Electrical equipment, products and materials should be supplied according to a schedule agreed with the electrical installation organization, which should provide for the priority delivery of materials and products included in the specifications for blocks to be manufactured at the assembly and packaging enterprises of electrical installation organizations.

1.6. The completion of the installation of electrical devices is the completion of individual tests of the mounted electrical equipment and the signing by the working commission of an act of acceptance of electrical equipment after an individual test. The beginning of individual tests of electrical equipment is the moment of introduction of an operating mode at a given electrical installation, announced by the customer on the basis of a notice from the commissioning and electrical installation organizations.

1.7. At each construction site, during the installation of electrical devices, special journals of the production of electrical work should be kept in accordance with SNiP 3.01.01-85, and upon completion of the work, the electrical installation organization is obliged to transfer to the general contractor the documentation presented by the working commission in accordance with SNiP III-3-81. The list of acts and protocols of inspections and tests is determined by the VSN, approved in accordance with the procedure established by SNiP 1.01.01-82.

2. PREPARATION FOR PRODUCTION

ELECTRICAL WORKS

2.1. The installation of electrical devices must be preceded by preparation in accordance with SNiP 3.01.01-85 and these rules.

2.2. Prior to the commencement of work at the facility, the following activities must be performed:

a) the working documentation was received in the quantity and within the timeframe determined by the Rules on construction contracts for capital

construction, approved by the decree of the Council of Ministers of the USSR, and the Regulations on the relationship of organizations, general contractors with subcontractors, approved by the USSR State Construction Committee and the USSR State Planning Committee;

b) the schedules for the supply of equipment, products and materials were agreed, taking into account the technological sequence of work, the list of electrical equipment installed with the involvement of the chief installation personnel of the supplier enterprises, the conditions for transporting heavy and large-sized electrical equipment to the installation site;

c) the necessary premises have been taken to accommodate teams of workers, engineering and technical workers, a production base, as well as for storing materials and tools with the provision of measures for labor protection, fire safety and environmental protection in accordance with SNiP 3.01.01-85;

d) a project for the production of works has been developed, the engineering and technical workers and foremen have been familiarized with the working documentation and estimates, organizational and technical solutions for the project for the production of works;

e) the acceptance of the construction part of the object for the installation of electrical devices in accordance with the requirements of these rules has been carried out and the measures for labor protection, fire safety and environmental protection during the work are carried out as provided for by the rules and regulations;

f) performed by the general contractor general construction and auxiliary works stipulated by the Regulations on the relationship of organizations - general contractors with subcontractors.

2.3. Equipment, products, materials and technical documentation must be transferred for installation in accordance with the Rules on Contracts for Capital Construction and the Regulations on the Relationship of Organizations - General Contractors with Subcontractors.

2.4. When the equipment is accepted for installation, it is inspected, the completeness is checked (without disassembly), the availability and validity of the manufacturer's warranties are checked.

2.5. The condition of the cables on the drums should be checked in the presence of the customer by means of an external examination. The results of the inspection are documented in an act.

2.6. When accepting prefabricated reinforced concrete structures of overhead lines (OHL), the following should be checked:

the dimensions of the elements, the position of the steel embedded parts, as well as the quality of the surfaces and the appearance of the elements. The specified parameters must comply with GOST 13015.0-83, GOST 22687.0-85, GOST 24762-81, GOST 26071-84, GOST 23613-79, as well as PUE;

the presence on the surface of reinforced concrete structures intended for installation in an aggressive environment, waterproofing made at the manufacturer.

2.7. Insulators and line fittings must meet the requirements of the relevant state standards and specifications. When accepting them, you should check:

availability of a manufacturer's passport for each batch of insulators and linear fittings, certifying their quality;

the absence of cracks, deformations, cavities, chips, damage to the glaze on the surface of the insulators, as well as swaying and turning of the steel reinforcement relative to the cement embedding or porcelain;

the absence of cracks, deformations, cavities and damage to galvanized steel and threads in linear reinforcement.

It is allowed to paint over minor damages of galvanized steel.

2.8. Elimination of defects and damages discovered during the transfer of electrical equipment is carried out in accordance with the Rules on Contracts for Capital Construction.

2.9. Electrical equipment, for which the standard storage period specified in state standards or technical conditions has expired, is accepted for installation only after a pre-installation audit, correction of defects and tests. The results of the work carried out must be entered in the forms, passports and other accompanying documentation, or an act of carrying out the indicated work must be drawn up.

2.10. Electrical equipment, products and materials accepted for installation should be stored in accordance with the requirements of state standards or technical specifications.

2.11. For large and complex objects with a large volume of cable lines in tunnels, canals and cable half-floors, as well as electrical equipment in electrical rooms, the construction organization design should define measures for advanced installation (against the installation of cable networks) of internal fire-fighting water supply systems, automatic fire extinguishing and automatic fire extinguishing systems. alarms provided by the working drawings.

2.12. In electrical rooms (switchboards, control rooms, substations and switchgears, machine rooms, battery rooms, cable tunnels and channels, cable half-floors, etc.), clean floors with drainage channels, the necessary slope and waterproofing and finishing works (plastering and painting ), embedded parts were installed and installation openings were left, the lifting and handling mechanisms and devices provided for by the project were mounted, pipe blocks, holes and openings for the passage of pipes and cables, grooves, niches and nests were prepared in accordance with the architectural and construction drawings and the work production project, power supply for temporary electric lighting in all rooms is made.

2.13. In buildings and structures, heating and ventilation systems must be put into operation, bridges, platforms and structures of suspended ceilings provided by the project for the installation and maintenance of electric lighting installations located at a height, as well as fixing structures for multi-lamp lamps (chandeliers) weighing over 100 kg; laid outside and inside buildings and structures asbestos-cement pipes and pipes and pipe blocks for the passage of cables provided for by the working construction drawings.

2.14. Foundations for electrical machines should be handed over for installation with fully completed construction and finishing works, installed air coolers and ventilation ducts, with benchmarks and axial strips (measurements) in accordance with the requirements of SNiP 3.02.01-83 and these rules.

2.15. On the supporting (rough) surfaces of foundations, depressions of no more than 10 mm and slopes up to 1: 100 are allowed. Deviations in building dimensions should be no more than: in terms of axial dimensions in the plan - plus 30 mm, in elevation marks of the surface of the foundations (excluding the height of the grout) - minus 30 mm, in terms of the dimensions of the ledges in the plan - minus 20 mm, in terms of the dimensions of wells - plus 20 mm, along the marks of the ledges in the recesses and wells - minus 20 mm, along the axes of the anchor bolts in the plan - ± 5 mm, along the axes of the embedded anchor devices in the plan - ± 10 mm, along the marks of the upper ends of the anchor bolts - ± 20 mm.

2.16. Delivery and acceptance of foundations for the installation of electrical equipment, the installation of which is carried out with the involvement of the installation supervision personnel, is carried out jointly with representatives of the organization that carries out installation supervision.

2.17. At the end of the finishing work in the battery rooms, acid- or alkali-resistant coatings of walls, ceilings and floors must be made, heating, ventilation, water supply and sewerage systems must be installed and tested.

2.18. Before the start of electrical work on open switchgears with a voltage of 35 kV and above, the construction organization must complete the construction of access roads, approaches and entrances, install bus and linear portals, build foundations for electrical equipment, cable channels with ceilings, fences around the switchgear, emergency discharge tanks oils, underground utilities and the planning of the territory is completed. In the structures of portals and foundations for the equipment, the embedded parts and fasteners provided for by the project must be installed, which are necessary for fastening the garlands of insulators and equipment. In cable ducts and tunnels, embedded parts must be installed for fastening cable structures and air ducts. The construction of a water supply system and other fire-prevention devices provided for by the project must also be completed.

2.19. The construction part of the outdoor switchgear and substations with a voltage of 330-750 kV should be accepted for installation for their full development, provided for by the project for the billing period.

2.20. Before the start of electrical work on the construction of overhead power lines with voltages up to 1000 V and above, preparatory work must be performed in accordance with SNiP 3.01.01-85, including:

Inventory structures were prepared at the locations of foreman's plots and temporary bases for storing materials and equipment; temporary access roads, bridges and assembly sites were built;

glades are arranged;

the demolition of buildings envisaged by the project and the reconstruction of intersected engineering structures located on or near the overhead line route and hindering the production of work were carried out.

2.21. The routes for laying the cable in the ground must be prepared for the beginning of its laying in the following volume: water is pumped out of the trench and stones, clods of earth, construction waste are removed; at the bottom of the trench there is a cushion of loosened earth; punctures were made in the ground at the intersection of the route with roads and other engineering structures, pipes were laid.

After laying the cables in the trench and the submission by the electrical installation organization of the act for the hidden work on laying the cables, the trench should be filled up.

2.22. Block sewerage routes for cable laying must be prepared taking into account the following requirements:

the design depth of the blocks was maintained from the planning level;

the correct laying and waterproofing of the joints of reinforced concrete blocks and pipes are ensured;

ensured the cleanliness and alignment of the channels;

there are double covers (the lower one with a lock) of the manholes of the wells, metal ladders or brackets for lowering into the well.

2.23. When constructing ramps for laying cables on their supporting structures (columns) and on spans, the embedded elements provided for by the project must be made for installing cable rollers, bypass devices and other devices.

2.24. The general contractor must present for acceptance for installation the construction readiness in residential buildings - by section, in public buildings - by floor (or by premises).

Reinforced concrete, gypsum concrete, expanded clay concrete floor panels, internal wall panels and partitions, reinforced concrete columns and prefabricated crossbars must have channels (pipes) for laying wires, niches, nests with embedded parts for installing plug sockets, switches, bells and bell buttons in accordance with working drawings. Cross-sections of channels and monolithic non-metallic pipes should not differ by more than 15% from those indicated in the working drawings.

The displacement of nests and niches at the junctions of adjacent building structures should not be more than 40 mm.

2.25. In buildings and structures handed over for the installation of electrical equipment, the general contractor must make holes, grooves, niches and nests in the foundations, walls, partitions, ceilings and coatings provided for by the architectural and construction drawings, which are necessary for the installation of electrical equipment and installation products, laying pipes for electrical wiring and electrical networks.

The indicated holes, grooves, niches and nests, which were not left in the building structures during their erection, are carried out by the general contractor in accordance with the architectural and construction drawings.

Holes with a diameter of less than 30 mm that cannot be taken into account in the development of drawings and which cannot be provided for in building structures according to the conditions of their manufacturing technology (holes in walls, partitions, ceilings only for installing dowels, pins and pins of various supporting and supporting structures) must carried out by the electrical installation organization at the place of work.

After completing the electrical work, the general contractor is obliged to seal the holes, grooves, niches and nests.

2.26. When accepting foundations for transformers, the presence and correctness of installation of anchors for fastening traction devices during rolling of transformers and foundations for jacks for turning rollers must be checked.

3. PRODUCTION OF ELECTRICAL INSTALLATION WORKS

GENERAL REQUIREMENTS

3.1. When loading, unloading, moving, lifting and installing electrical equipment, measures must be taken to protect it from damage, while heavy electrical equipment must be securely slinged to the parts provided for this purpose or in the places specified by the manufacturer.

3.2. Electrical equipment during installation is not subject to disassembly and revision, except for cases when it is provided for by state and industry standards or technical conditions agreed in the prescribed manner.

Disassembly of equipment received sealed from the manufacturer is prohibited.

3.3. Electrical equipment and cable products that are deformed or with damage to the protective coatings are not subject to installation until the damage and defects are eliminated in the prescribed manner.

3.4. In the production of electrical work, standard sets of special tools should be used for the types of electrical work, as well as mechanisms and devices designed for this purpose.

3.5. As supporting structures and fasteners for the installation of trolleys, bus ducts, trays, boxes, hinged shields and control posts, protective and starting equipment and lamps, factory-made products should be used that have increased assembly readiness (with a protective coating, adapted for fastening without welding and not requiring large labor costs for machining).

Fastening of supporting structures should be carried out by welding to embedded parts provided in building elements, or by fasteners (dowels, pins, pins, etc.). The method of fastening must be indicated in the working drawings.

3.6. The color designation of current-carrying buses of switchgears, trolleys, grounding buses, overhead lines should be performed in accordance with the instructions given in the project.

3.7. During the performance of work, the electrical installation organization must comply with the requirements of GOST 12.1.004-76 and the Fire Safety Rules in the performance of construction and installation works. When the operational regime is introduced at the facility, ensuring fire safety is the responsibility of the customer.

CONTACT CONNECTIONS

3.8. Collapsible connections of buses and cores of wires and cables to contact terminals of electrical equipment, installation products and bus ducts must meet the requirements of GOST 10434-82.

3.9. In the places where the conductors of wires and cables are connected, a supply of wire or cable should be provided to ensure the possibility of re-connection.

3.10. The joints and branches must be accessible for inspection and repair. The insulation of connections and branches should be equivalent to the insulation of the cores of the wires and cables to be connected.

At the points of connections and branches, wires and cables should not be subjected to mechanical stress.

3.11. The termination of the cable core with impregnated paper insulation should be performed with sealed current-carrying fittings (lugs), which do not allow the cable impregnating compound to leak out.

3.12. Busbar connections and branches should be made, as a rule, non-separable (by welding).

In places where collapsible joints are required, busbar connections should be made with bolts or pressure plates. The number of collapsible joints should be minimal.

3.13. Connections of wires of overhead lines with voltage up to 20 kV should be performed:

a) in the loops of the anchor-angle type supports: with clamps - anchor and branch wedge; connecting oval, mounted by the crimp method; looped dies, with the help of thermite cartridges, and wires of different brands and sections - with hardware pressed clamps;

b) in the spans: connecting oval clamps, mounted by twisting.

Single-wire wires are allowed to be connected by twisting. Butt welding of solid wires is not allowed.

3.14. The connection of overhead lines with a voltage higher than 20 kV must be performed:

a) in the loops of the anchor-angle type supports:

steel-aluminum wires with a cross-section of 240 sq. mm and above - with the help of thermite cartridges and crimping with the help of explosion energy;

steel-aluminum wires with a cross-section of 500 sq. mm and above - using crimp connectors;

wires of different brands - with bolt clamps;

wires made of aluminum alloy - with loop-type clamps or oval connectors, mounted by the crimping method;

b) in the spans:

steel-aluminum wires with a cross-section up to 185 sq. mm and steel ropes with a cross-section up to 50 sq. mm - oval connectors, mounted by twisting;

steel ropes with a cross section of 70-95 sq. mm with oval connectors, mounted by crimping or crimping with additional thermite welding of the ends;

steel-aluminum wires with a cross-section of 240-400 sq. mm with connecting clamps, mounted by continuous crimping and crimping using explosion energy;

steel-aluminum wires with a cross section of 500 sq. mm and more - with connecting clamps, mounted by the method of continuous crimping.

3.15. The connection of copper and steel-copper ropes with a cross-section of 35-120 sq. Mm, as well as aluminum wires with a cross-section of 120-185 sq. Mm during the installation of contact networks should be performed with oval connectors, steel ropes - with clamps with a connecting strip between them. Steel-copper ropes with a cross section of 50-95 sq. Mm are allowed to be joined with wedge clamps with a connecting bar between them.

ELECTRICAL WIRING

General requirements

3.16. The rules of this subsection apply to the installation of electrical wiring for power, lighting and secondary circuits with voltages up to 1000 V AC and DC, laid inside and outside buildings and structures with insulated installation wires of all sections and unarmored cables with rubber or plastic insulation with a cross section of up to 16 sq. mm.

3.17. Installation of control cables should be carried out taking into account the requirements of paragraphs. 3.56-3.106.

3.18. Passages of non-armored cables, protected and unprotected wires through fireproof walls (partitions) and interfloor ceilings must be made in pipe sections, or in boxes, or openings, and through combustible ones - in steel pipe sections.

Openings in walls and ceilings must have a frame that excludes their destruction during operation. In places where wires and cables pass through walls, ceilings or their exit to the outside, gaps between wires, cables and a pipe (box, opening) should be sealed with an easily removable mass from a non-combustible material.

Sealing should be done on each side of the pipe (duct, etc.).

In the case of open laying of non-metallic pipes, the sealing of the places of their passage through fire barriers should be made with non-combustible materials immediately after laying the cables or wires into the pipes.

Sealing the gaps between pipes (box, opening) and the building structure (see clause 2.25), as well as between wires and cables laid in pipes (boxes, openings), with an easily removable mass from a non-combustible material should provide fire resistance corresponding to the fire resistance of the building structure ...

Laying wires and cables on trays and boxes

3.19. The design and degree of protection of trays and boxes, as well as the method of laying wires and cables on trays and in boxes (in bulk, bundles, multilayer, etc.) must be specified in the project.

3.20. The way the boxes are installed should not allow moisture to accumulate in them. The boxes used for open electrical wiring should have, as a rule, removable or opening covers.

3.21. For hidden gaskets, blind ducts should be used.

3.22. Wires and cables laid in boxes and on trays must be marked at the beginning and at the end of trays and boxes, as well as at the points of their connection to electrical equipment, and cables, in addition, also on the turns of the track and on branches.

3.23. Fasteners of unprotected wires and cables with a metal sheath with metal brackets or bands must be made with gaskets made of elastic insulating materials.

Laying wires on insulating supports

3.24. When laying on insulating supports, the connection or branching of the wires should be carried out directly at the insulator, clip, roller or on them.

3.25. The distances between the attachment points along the route and between the axes of parallel laid unprotected insulated wires on insulating supports should be indicated in the project.

3.26. Hooks and brackets with insulators should be fixed only in the main material of the walls, and rollers and clamps for wires with a cross section of up to 4 mm2 incl. can be fixed to plaster or cladding of wooden buildings. Hook insulators must be securely fastened.

3.27. When fastening the rollers with wood grouses, metal and elastic washers should be placed under the heads of the wood grouses, and when fastening the rollers on metal, elastic washers should be placed under their bases.

Laying wires and cables on a steel rope

3.28. Wires and cables (in polyvinyl chloride, nitrite, lead or aluminum sheaths with rubber or polyvinyl chloride insulation) must be fixed to the supporting steel rope or to the wire with bandages or clamps installed at distances of no more than 0.5 m from each other.

3.29. Cables and wires laid on the ropes, at the points of their transition from the rope to the structures of buildings, must be unloaded from mechanical forces.

Vertical suspensions of the wiring on a steel rope should be located, as a rule, in the places where branch boxes, plug connectors, lamps, etc. are installed. The sag arrow of the rope in the spans between the fasteners should be within 1/40 - 1/60 of the span length. Splicing of ropes in the span between end fixtures is not allowed.

3.30. Guy braces should be installed on the wire rope to prevent the lighting wiring from swaying. The number of stretch marks should be determined in the working drawings.

3.31. For branches from special cable wires, special boxes must be used to create a cable loop, as well as a supply of cores necessary to connect an outgoing line using branch clamps without cutting the line.

Laying installation wires on building foundations

and inside the main building structures

3.32. Open and hidden laying of installation wires is not allowed at temperatures below minus 15 ° C.

3.33. With hidden laying of wires under a layer of plaster or in thin-walled (up to 80 mm) partitions, wires should be laid parallel to the architectural and construction lines. The distance of horizontally laid wires from floor slabs should not exceed 150 mm. In building structures with a thickness of more than 80 mm, wires must be laid along the shortest routes.

3.34. All connections and branches of the installation wires must be made by welding, crimping in sleeves or using clamps in branch boxes.

Metal junction boxes in the places where wires are inserted into them must have bushings made of insulating materials. It is allowed to use pieces of PVC tube instead of bushings. In dry rooms, it is allowed to place branches of wires in the nests and niches of walls and floors, as well as in the voids of the floors. The walls of the nests and niches should be smooth, the branches of the wires located in the nests and niches should be covered with covers made of non-combustible material.

3.35. Fastening of flat wires with hidden laying should ensure their snug fit to the building foundations. In this case, the distances between the attachment points should be:

a) when laying on horizontal and vertical sections of plastering wire bundles - no more than 0.5 m; single wires -0.9 m;

b) when covering wires with dry plaster - up to 1.2 m.

3.36. The plinth wiring device must provide separate routing of power and low-current wires.

3.37. The fixing of the plinth should ensure its tight fit to the building bases, while the pull-off force should be at least 190 N, and the gap between the plinth, wall and floor should be no more than 2 mm. Skirting boards should be made of non-combustible and non-combustible materials with electrical insulating properties.

3.38. In accordance with GOST 12504-80, GOST 12767-80 and GOST 9574-80, the panels must provide for internal channels or embedded plastic pipes and embedded elements for hidden replaceable electrical wiring, sockets and holes for installing junction boxes, switches and sockets.

Holes for wiring accessories and broaching niches in the wall panels of adjacent apartments should not be through. If, according to the conditions of the manufacturing technology, it is not possible to make holes blind, then sound-insulating gaskets made of vinyl foam or other non-combustible sound-insulating material must be laid in them.

3.39. The installation of pipes and boxes in reinforcing cages should be carried out on the conductors according to the working drawings that determine the attachment points for the installation, branch and ceiling boxes. To ensure that the boxes are positioned flush with the surface of the panels after molding, they should be fixed to the reinforcing cage in such a way that when the boxes are installed in blocks, the height of the block corresponds to the thickness of the panel, and when the boxes are installed separately to prevent their displacement inside the panels, the front surface of the boxes should protrude beyond the plane of the reinforcement cage. by 30-35 mm.

3.40. The channels should have a smooth surface along their entire length, without sagging and sharp corners.

The thickness of the protective layer above the channel (pipe) must be at least 10 mm.

The length of channels between broaching niches or boxes should be no more than 8 m.

Laying wires and cables in steel pipes

3.41. Steel pipes are allowed to be used for electrical wiring only in cases specially justified in the project in accordance with the requirements of regulatory documents approved in the manner established by SNiP 1.01.01-82.

3.42. Steel pipes used for electrical wiring must have an inner surface that excludes damage to the insulation of the wires when they are pulled into the pipe and an anti-corrosion coating of the outer surface. For pipes embedded in building structures, an external anti-corrosion coating is not required. Pipes laid in rooms with a chemically active environment, inside and outside, must have an anti-corrosion coating that is resistant to the conditions of this environment. In places where wires exit from steel pipes, insulating sleeves should be installed.

3.43. Steel pipes for electrical wiring, laid in the foundations for technological equipment, must be fixed to supporting structures or to reinforcement before concreting the foundations. In places where pipes exit from the foundation into the ground, the measures provided for in the working drawings must be carried out against the shearing of the pipes in case of sedimentation of the ground or foundation.

3.44. In the places where the pipes intersect the expansion and sedimentary joints, compensating devices must be made in accordance with the instructions in the working drawings.

3.45. The distances between the attachment points of openly laid steel pipes should not exceed the values ​​indicated in table. 1. Fastening steel pipes of electrical wiring directly to technological pipelines, as well as their welding directly to various structures are not allowed.

Table 1

Nominal bore of pipes, mm

Nominal bore of pipes, mm

The greatest permissible distances between attachment points, m

3.46. When bending pipes, as a rule, normalized angles of rotation of 90, 120 and 135 ° and normalized bending radii of 400, 800 and 1000 mm should be used. A bending radius of 400 mm should be used for pipes laid in ceilings and for vertical outlets; 800 and 1000 mm - when laying pipes in monolithic foundations and when laying cables with single-wire conductors in them. When preparing packages and blocks of pipes, you should also adhere to the specified normalized angles and bending radii.

3.47. When laying wires in vertically laid pipes (risers), their fastening should be provided, and the fastening points should be spaced from each other at a distance not exceeding, m:

for wires up to 50 sq. mm incl. ................... thirty

the same, from 70 to 150 sq. mm incl. .................. twenty

"" 185 "240 sq. Mm" ....................... 15

Fastening of wires should be carried out using clamps or clamps in broaching or branch boxes or at the ends of pipes.

3.48. Pipes with hidden laying in the floor must be buried at least 20 mm and protected with a layer of cement mortar. It is allowed to install branch and pull-out boxes in the floor, for example, for modular wiring.

3.49. The distances between broaching boxes (boxes) should not exceed, m: on straight sections 75, with one pipe bend - 50, with two - 40, with three - 20.

Wires and cables in pipes must lie freely, without tension. The diameter of the pipes should be taken in accordance with the instructions in the working drawings.

Laying wires and cables in non-metallic pipes

3.50. The laying of non-metallic (plastic) pipes for tightening wires and cables in them must be carried out in accordance with the working drawings at an air temperature of at least minus 20 and no higher than plus 60 ° C.

In foundations, plastic pipes (usually polyethylene) should be laid only on horizontally compacted soil or a layer of concrete.

In foundations up to 2 m deep, PVC pipes can be laid. In this case, measures must be taken against mechanical damage during concreting and backfilling of soil.

3.51. The fastening of openly laid non-metallic pipes must allow their free movement (movable fastening) during linear expansion or contraction from changes in the ambient temperature. The distances between the points of installation of movable mounts must correspond to those indicated in table. 2.

table 2

Outer pipe diameter, mm

Outer pipe diameter, mm

Distances between attachment points for horizontal and vertical laying, mm

3.52. The thickness of the concrete solution above the pipes (single and blocks) when they are embedded in the preparation of the floors must be at least 20 mm. At the intersection of pipe routes, a protective layer of concrete mortar between the pipes is not required. In this case, the depth of the top row must comply with the above requirements. If, when crossing pipes, it is impossible to ensure the required depth of the pipes, they should be protected from mechanical damage by installing metal sleeves, casings or other means in accordance with the instructions in the working drawings.

3.53. Protection against mechanical damage at the intersection of electrical wiring laid in the floor in plastic pipes with the routes of in-house transport with a concrete layer of 100 mm or more is not required. The exit of plastic pipes from foundations, gravy-floors and other building structures should be made with segments or elbows of polyvinyl chloride pipes, and if mechanical damage is possible, with segments from thin-walled steel pipes.

3.54. When PVC pipes exit the walls in places of possible mechanical damage, they should be protected with steel structures to a height of up to 1.5 m or exit the wall with thin-walled steel pipes.

3.55. The connection of plastic pipes must be carried out:

polyethylene - tight fit with couplings, hot casing in a socket, couplings made of heat-shrinkable materials, welding;

polyvinyl chloride - tight fit in the socket or with the help of couplings. Bonding by gluing is allowed.

CABLE LINES

General requirements

3.56. These rules should be observed when installing power cable lines with a voltage of up to 220 kV.

Installation of cable lines of the subway, mines, mines should be carried out taking into account the requirements of the VSN, approved in the manner established by SNiP 1.01.01-82.

3.57. The smallest permissible bending radii of cables and the permissible level difference between the highest and lowest points of the location of cables with impregnated paper insulation on the route must comply with the requirements of GOST 24183-80 *, GOST 16441-78, GOST 24334-80, GOST 1508-78 * E and approved technical conditions.

3.58. When laying cables, measures should be taken to protect them from mechanical damage. The pulling forces of cables up to 35 kV should be within the values ​​given in table. 3. Winches and other traction devices must be equipped with adjustable limiting devices to release the tension when forces are exceeding permissible. Broaching devices, crimping the cable (drive rollers), as well as turning devices must exclude the possibility of deformation of the cable.

For cables with a voltage of 110-220 kV, the permissible tensile forces are given in clause 3.100.

3.59. Cables should be laid with a margin of 1–2% in length. In trenches and on solid surfaces inside buildings and structures, the reserve is achieved by laying the cable with a "snake", and along cable structures (brackets) this reserve is used to form a sag arrow.

It is not allowed to lay the cable stock in the form of rings (turns).

Table 3

Efforts gravitating for

aluminum

Tension forces for the veins, kN,

cables up to 35, kV

cable, mm2

sheath, kN, cable voltage, kV

aluminum stranded

aluminum solid

1,7 1,8 2,3 2,9 3,4 3,9 5,9 6,4 7,4

2,8 2,9 3,4 3,9 4,4 4,9 6,4 7,4 9,3

3,7 3,9 4,4 4,9 5,7 6,4 7,4 8,3 9,8

_____________________

* Made of soft aluminum with a relative elongation of not more than 30%.

Notes:

1. Pulling a cable with a plastic or lead sheath is allowed only by the conductors.

2. The tensile forces of the cable when pulling it through the block sewer are given in table. 4.

3. Cables armored with round wire should be pulled by the wires. Allowable voltage 70-100 N / sq.mm.

4. Control cables and armored and non-armored power cables with a cross-section of up to 3 x 16 sq. Mm, in contrast to the cables of large cross-sections given in this table, are allowed to be laid mechanically by pulling for the armor or for the sheath using a wire stocking, while the pulling forces should not exceed 1 kN.

3.60. Cables laid horizontally along structures, walls, ceilings, trusses, etc., should be rigidly fixed at the end points, directly at the end couplings, at the bends of the track, on both sides of the bends and at the couplings and stop couplings.

3.61. Cables that are routed vertically through structures and walls must be fixed to each cable structure.

3.62. The distances between the supporting structures are taken in accordance with the working drawings. When laying power and control cables with an aluminum sheath on supporting structures with a distance of 6000 mm, a residual deflection in the middle of the span must be ensured: 250-300 mm when laying on ramps and galleries, at least 100-150 mm in other cable structures.

Structures on which non-armored cables are laid must have a design that excludes the possibility of mechanical damage to the cable sheaths.

In places of rigid attachment of unarmoured cables with a lead or aluminum sheath, gaskets of elastic material (for example, sheet rubber, sheet polyvinyl chloride) should be laid on structures; non-armored cables with a plastic sheath or plastic hose, as well as armored cables may be fastened to structures with brackets (clamps) without gaskets.

3.63. Armored and non-armored cables indoors and outdoors in places where mechanical damage is possible (movement of vehicles, cargo and mechanisms, accessibility to unqualified personnel) must be protected to a safe height, but not less than 2 m from the ground or floor level and at a depth of 0 , 3 m in the ground.

3.64. The ends of all cables, in which the sealing was broken during the laying process, must be temporarily sealed before the installation of the couplings and end sleeves.

3.65. Passages of cables through walls, partitions and ceilings in industrial premises and cable structures must be carried out through lengths of non-metallic pipes (asbestos free-flow, plastic, etc.), textured holes in reinforced concrete structures or open openings. Gaps in pipe sections, holes and openings after laying cables should be sealed with non-combustible material, for example, cement with sand by volume 1:10, clay with sand - 1: 3, clay with cement and sand - 1.5: 1: 11, perlite expanded with plaster of paris - 1: 2, etc., across the entire thickness of the wall or partition.

The gaps in the passages through the walls may not be repaired if these walls are not fire barriers.

3.66. Before laying the cable, the trench should be inspected to identify places on the route containing substances that have a destructive effect on the metal cover and sheath of the cable (salt marshes, lime, water, bulk soil containing slag or construction waste, areas located closer than 2 m from cesspools and garbage holes, etc.). If it is impossible to bypass these places, the cable should be laid in clean neutral soil in free-flow asbestos-cement pipes, covered inside and outside with a bitumen composition, etc. When filling the cable with neutral soil, the trench should be additionally expanded on both sides by 0.5-0, 6 m and deepened by 0.3-0.4 m.

3.67. Cable entries into buildings, cable structures and other premises must be made in asbestos-cement gravity pipes in the billed holes of reinforced concrete structures. The ends of the pipes should protrude from the wall of the building into the trench, and if there is a blind area, at least 0.6 m beyond the line of the latter and have a slope towards the trench.

3.68. When laying several cables in a trench, the ends of the cables intended for the subsequent installation of couplings and stop couplings should be positioned with a shift of the connection points by at least 2 m.At the same time, a reserve of cable with a length necessary for checking the insulation for moisture and installing the coupling must be left. as well as laying the arc of the compensator (with a length at each end of at least 350 mm for cables with a voltage of up to 10 kV and at least 400 mm for cables with a voltage of 20 and 35 kV).

3.69. In cramped conditions with large cable flows, it is allowed to place compensators in a vertical plane below the level of cable laying. In this case, the sleeve remains at the level of the cable routing.

3.70. The cable laid in the trench must be covered with the first layer of earth, a mechanical protection or a signal tape must be laid, after which representatives of the electrical installation and construction organizations, together with the customer's representative, must inspect the route with the drawing up of an act for hidden work.

3.71. The trench should be finally backfilled and tamped after the installation of couplings and testing of the line with increased voltage.

3.72. Filling the trench with lumps of frozen soil, soil containing stones, pieces of metal, etc., is not allowed.

3.73. Trenchless laying from a self-propelled or movable knife cable layer is allowed for 1-2 armored cables with a voltage of up to 10 kV with a lead or aluminum sheath on cable routes remote from engineering structures. In city power grids and on industrial enterprises trenchless laying is allowed only on extended sections in the absence of underground communications on the route, intersections with engineering structures, natural obstacles and hard surfaces.

3.74. When laying a cable line route in undeveloped areas along the entire route, identification marks must be installed on concrete posts or on special signage plates that are placed at the turns of the route, at the locations of couplings, on both sides of intersections with roads and underground structures, at entrances to buildings and every 100 m on straight sections.

On arable land, identification signs should be installed at least 500 m.

Block sewerage installation

3.75. The total length of the unit channel according to the conditions of the maximum permissible tensile forces for unarmoured cables with a lead sheath and copper conductors should not exceed the following values:

Cable cross-section, sq. Mm .... up to 3x50 3x70 3x95 and above

Maximum length, m ..... 145 115 108

For non-armored cables with aluminum conductors with a cross section of 95 sq. Mm and above, in a lead or plastic sheath, the channel length should not exceed 150 m.

3.76. The maximum permissible tensile forces of unarmored cables with a lead sheath and with copper or aluminum conductors when attaching the traction rope to the conductors, as well as the required efforts to pull 100 m of cable through the block sewer are given in Table. 4.

Table 4

Unarmoured cable cores with

lead

Cable cross-section, mm2

Allowable tensile force, kN

Required tensile force per 100 m of cable, kN, voltage, kV

shell

Aluminum

Note.

To reduce the pulling forces when pulling the cable, it should be coated with a grease that does not contain substances that are harmful to the cable sheath (grease, grease).

3.77. For non-armored cables with a plastic sheath, the maximum permissible tensile forces should be taken according to table. 4 with correction factors for cores:

copper ........................................ 0,7

made of solid aluminum .......................... 0.5

"soft" .......................... 0.25

Laying in cable structures

and industrial premises

3.78. When laying in cable structures, collectors and industrial premises, cables should not have outer protective covers made of combustible materials. Metal sheaths and cable armor that have a non-combustible anticorrosive (for example, galvanic) coating made at the manufacturer's plant are not subject to painting after installation.

3.79. Cables in cable structures and collectors of residential areas should be laid, as a rule, in whole building lengths, avoiding, if possible, the use of couplings in them.

Cables laid horizontally along structures on open overpasses (cable and technological), except for fastening in places according to clause 3.60, must be fixed in order to avoid displacement under the influence of wind loads on straight horizontal sections of the route in accordance with the instructions given in the project.

3.80. Cables in an aluminum sheath without an outer cover when laying them along plastered and concrete walls, trusses and columns must be at least 25 mm away from the surface of building structures. On the painted surfaces of these structures, it is allowed to lay such cables without a gap.

Steel rope gasket

3.81. The diameter and brand of the rope, as well as the distance between the anchor and intermediate fastenings of the rope, are determined in the working drawings. The sag of the rope after hanging the cables should be within 1/40 - 1/60 of the span length. Distances between cable hangers should be no more than 800 - 1000 mm.

3.82. Anchoring end structures must be anchored to the columns or walls of the building. Fastening them to beams and trusses is not allowed.

3.83. Steel rope and other metal parts for laying cables on a rope outdoors, regardless of the presence of a galvanic coating, must be coated with a lubricant (for example, grease). Indoors, galvanized wire rope should only be coated with lubricant if it is likely to corrode from an aggressive environment.

Laying in permafrost soils

3.84. The depth of laying cables in permafrost is determined in the working drawings.

3.85. Local soil used for trench backfilling must be crushed and compacted. Ice and snow are not allowed in the trench. The soil for the embankment should be taken from places at least 5 m from the axis of the cable route. The soil in the trench after settling should be covered with a moss-peat layer.

As additional measures against the occurrence of frost cracks should be used:

backfilling of a trench with a cable with sandy or gravel-pebble soil;

installation of drainage ditches or slots up to 0.6 m deep, located on both sides of the route at a distance of 2-3 m from its axis;

sowing the cable route with grasses and casing with shrubs.

Low temperature gasket

3.86. Laying cables in the cold season without preheating is allowed only in cases where the air temperature has not dropped, at least temporarily, below during 24 hours before the start of work:

0 ° С - for power armored and non-armored cables with paper insulation (viscous, non-flowing and depleted impregnated) in a lead or aluminum sheath;

minus 5 ° С - for oil-filled cables of low and high pressure;

minus 7 ° С - for control and power cables with voltage up to 35 kV with plastic or rubber insulation and sheathing with fibrous materials in a protective cover, as well as with armor made of steel tapes or wire;

minus 15 ° С - for control and power cables with voltage up to 10 kV with PVC or rubber insulation and sheath without fibrous materials in a protective cover, as well as with armor made of profiled galvanized steel tape;

minus 20 ° С - for non-armored control and power cables with polyethylene insulation and sheath without fibrous materials in a protective cover, as well as with rubber insulation in a lead sheath.

3.87. Short-term drops in temperature within 2-3 hours (night frosts) should not be taken into account if the temperature was positive in the previous period of time.

3.88. At an air temperature below that specified in clause 3.86, the cables must be preheated and laid within the following periods:

more than 1 hour ................ from 0 to minus 10 ° С

"40 min ............. from minus 10 to minus 20 ° С

"30 minutes ............. from minus 20 ° С and below

3.89. Unarmoured cables with an aluminum sheath in a PVC hose, even preheated ones, are not allowed to be laid at an ambient temperature below minus 20 ° C.

3.90. At ambient temperatures below minus 40 ° C, laying cables of all brands is not allowed.

3.91. When laying the heated cable, it must not bend less than the allowable radius. It is necessary to lay it in a trench with a snake with a margin of length in accordance with clause 3.59. Immediately after installation, the cable should be backfilled with the first layer of loosened soil. Finally, fill the trench with soil and compact the backfill after the cable has cooled.

Installation of sleeves for cables with voltage up to 35 kV

3.92. Installation of sleeves for power cables with voltage up to 35 kV and control cables should be carried out in accordance with the departmental technological instructions, approved in accordance with the established procedure.

3.93. Types of couplings and terminations for power cables with voltage up to 35 kV with paper and plastic insulation and control cables, as well as methods of connecting and terminating cable cores must be specified in the project.

3.94. The clear distance between the coupling body and the nearest buried cable must be at least 250 mm. On steeply sloping routes (over 20 ° to the horizontal), as a rule, do not install couplings. If it is necessary to install couplings in such areas, they should be located on horizontal platforms. To ensure the possibility of re-installation of the couplings in the event of their damage, on both sides of the coupling, a cable reserve must be left in the form of a compensator (see section 3.68).

3.95. Cables in cable structures should be laid, as a rule, without making couplings on them. If it is necessary to use connecting sleeves on cables with a voltage of 6-35 kV, each of them must be laid on a separate supporting structure and enclosed in a fireproof protective cover for localization of a fire (manufactured in accordance with the approved normative and technical documentation). In addition, the joint must be separated from the upper and lower cables by fireproof protective barriers with a fire resistance of at least 0.25 hours.

3.96. Couplings for cables laid in blocks must be located in wells.

3.97. On a track consisting of a through tunnel, passing into a semi-through tunnel or a no-through channel, the couplings must be located in the through tunnel.

Features of the installation of cable lines with a voltage of 110-220 kV

3.98. Working drawings of cable lines with oil-filled cables for a voltage of 110-220 kV and cables with plastic (vulcanized polyethylene) insulation with a voltage of 110 kV and PPR for their installation must be agreed with the cable manufacturer.

3.99. The temperature of the cable and the ambient air during installation must not be lower than: minus 5 ° С - for an oil-filled cable and minus 10 ° С - for a cable with plastic insulation. At lower temperatures, the gasket can only be approved in accordance with the PPR.

3.100. For mechanized laying, cables with round wire armor should be pulled by the wires using a special grip that ensures an even distribution of the load between the wires of the armor. In this case, in order to avoid deformation of the lead sheath, the total tensile force should not exceed 25 kN. Unarmoured cables may only be pulled by the cores using a grip mounted on the upper end of the cable on the drum. The largest allowable tensile force is determined from the calculation: 50 MPa (N / sq.mm) - for copper conductors, 40 MPa (N / sq.mm) - for solid aluminum conductors and 20 MPa (N / sq.mm) - for soft aluminum cores.

3.101. The traction winch must be equipped with a recording device and an automatic shutdown device when the maximum permissible tension value is exceeded. The recording device must be equipped with a self-recording device. Reliable telephone or VHF communication must be established during the laying between the locations of the drum with the cable, the winch, the turns of the track, transitions and intersections with other communications.

3.102. Cables laid on cable structures with a span of 0.8-1 m between them must be fixed on all supports with aluminum brackets with two layers of rubber 2 mm thick, unless otherwise indicated in the working documentation.

Cable marking

3.103. Each cable line must be marked and have its own number or name.

3.104. Open cables and cable glands must be labeled.

On cables laid in cable structures, tags should be installed at least every 50-70 m, as well as in places where the route direction changes, on both sides of passages through interfloor floors, walls and partitions, in places where the cable is input (output) into trenches and cable structures.

On hidden cables in pipes or blocks, the tags should be installed at the end points at the end couplings, in the wells and chambers of the block sewer, as well as at each coupling.

On hidden cables in trenches, tags are installed at the end points and at each coupling.

3.105. Tags should be used: in dry rooms - made of plastic, steel or aluminum; in damp rooms, outside buildings and in the ground - made of plastic.

Designations on tags for underground cables and cables laid in rooms with a chemically active environment should be made by stamping, punching or burning. For cables laid in other conditions, the designation is allowed to be applied with indelible paint.

3.106. The tags should be fixed on the cables with nylon thread or galvanized steel wire with a diameter of 1-2 mm, or with a plastic tape with a button. The place where the tag is attached to the cable with a wire and the wire itself in damp rooms, outside buildings and in the ground must be covered with bitumen to protect it from moisture.

CURRENT DUCTS WITH VOLTAGE UP TO 35 kV

Bus ducts up to 1 kV (busbars)

3.107. Sections with expansion joints and flexible sections of main bus ducts must be fixed on two supporting structures installed symmetrically on both sides of the flexible part of the bus duct section. The fastening of the busbar trunking to the supporting structures in horizontal sections should be carried out with clamps, which provide the possibility of displacement of the busbar when the temperature changes. The busbar, laid in vertical sections, must be rigidly bolted to the structures.

For the convenience of removing the covers (casing parts), as well as to ensure cooling, the busbar trunking should be installed with a gap of 50 mm from the walls or other building structures of the building.

Pipes or metal sleeves with wires must be inserted into the branch sections through the holes made in the busbar casings. Pipes should be terminated with sleeves.

3.108. The non-detachable connection of the busbars of the sections of the main bus duct must be welded, the connections of the distribution and lighting bus ducts must be collapsible (bolted).

The connection of the trolley busbar sections must be carried out using special connecting parts. The collector carriage must move freely along the guides along the slot of the box of the mounted trolley busbar.

Open conductors with voltage of 6-35 kV

3.109. These rules must be observed when installing rigid and flexible conductors with a voltage of 6-35 kV.

3.110. As a rule, all work on the installation of conductors should be carried out with preliminary preparation of units and sections of blocks at procurement and assembly sites, workshops or factories.

3.111. All connections and branches of buses and wires are carried out in accordance with the requirements of paragraphs. 3.8; 3.13; 3.14.

3.112. In the places of bolted and hinged joints, measures must be provided to prevent self-loosening (cotter pins, locknuts - locking, disc or spring washers). All fasteners must have an anti-corrosion coating (galvanized, passivated).

3.113. Installation of supports for open conductors is carried out in accordance with paragraphs. 3.129-3.146.

3.114. When adjusting the suspension of the flexible conductor, uniform tension of all its links must be ensured.

3.115. Connections of wires of flexible conductors should be made in the middle of the span after rolling out the wires before drawing them out.

AIR POWER LINES

Felling of glades

3.116. The clearing along the overhead line must be cleared of cut trees and bushes. Commercial timber and firewood should be stacked outside the clearing.

The distances from wires to green spaces and from the axis of the route to stacks of combustible materials must be indicated in the project. Cutting down shrubs on loose soils, steep slopes and areas flooded during floods is not allowed.

3.117. Burning of branches and other felling residues should be carried out within the permitted period of time.

3.118. The wood left in stacks on the overhead line route for a fire hazardous period, as well as the remaining `` shafts '' of felling residues for this period, should be bordered by a mineralized strip 1 m wide, from which grass vegetation, forest litter and other combustible materials should be completely removed to the mineral layer soil.

Construction of pits and foundations for supports

3.119. The construction of foundation pits should be carried out in accordance with the rules for the production of work set forth in SNiP III-8-76 and SNiP 3.02.01-83.

3.120. Pits for support posts should be developed, as a rule, with drilling machines. The development of pits must be carried out up to the design level.

3.121. The development of pits in rocky, frozen, permafrost soils is allowed to be carried out by explosions for "ejection" or "loosening" in accordance with the Unified Safety Rules for Blasting Operations, approved by the USSR State Technical Supervision Service.

In this case, the ditches should be underworked to the design mark by 100-200 mm, followed by revision with jackhammers.

3.122. The pits should be drained by pumping out water before installing the foundations.

3.123. In winter, the development of pits, as well as the installation of foundations in them, should be carried out as soon as possible, excluding freezing of the bottom of the pits.

3.124. The construction of foundations on permafrost soils is carried out while maintaining the natural frozen state of the soil in accordance with SNiP II-18-76 and SNiP 3.02.01-83.

3.125. Prefabricated reinforced concrete foundations and piles must meet the requirements of SNiP 2.02.01-83, SNiP II-17-77, SNiP II-21-75, SNiP II-28-73 and the draft of standard structures.

When installing prefabricated reinforced concrete foundations and driving piles, one should be guided by the rules for the production of work set forth in SNiP 3.02.01-83 and SNiP III-16-80.

When constructing monolithic reinforced concrete foundations, SNiP III-15-76 should be followed.

3.126. The welded or bolted joints of the uprights to the foundation slabs must be protected against corrosion. Before welding, the parts of the joints must be free of rust. Reinforced concrete foundations with a concrete cover of less than 30 mm, as well as foundations installed in aggressive soils, must be protected by waterproofing.

Pickets with an aggressive environment must be specified in the project.

3.127. Backfilling of pits with soil should be carried out immediately after the installation and alignment of the foundations. The soil must be carefully compacted by layer-by-layer compaction.

The templates used for the construction of foundations should be removed after backfilling at least half the depth of the pits.

The height of the backfill of the pits should be taken taking into account the possible subsidence of the soil. When installing foundation embankments, the slope should have a steepness of no more than 1: 1.5 (the ratio of the slope height to the base), depending on the type of soil.

The soil for backfilling the pits should be protected from freezing.

3.128. Tolerances for the installation of prefabricated reinforced concrete foundations are given in table. 5.

Table 5

Deviations

Support tolerances

free-standing

guyed

Levels of the bottom of the pits

Distances between the axes of the foundations in the plan

Elevations of the top of the foundations *

The angle of inclination of the longitudinal axis of the foundation rack

Angle of inclination of the axis of the V-shaped anchor bolt

Displacement of the center of the foundation in plan

__________________

* The difference in elevation must be compensated for when mounting the support using steel shims.

Assembly and installation of supports

3.129. The size of the platform for assembling and installing the support should be taken in accordance with technological map or the assembly diagram of the support specified in the PPR.

3.130. In the manufacture, installation and acceptance of steel structures of overhead line supports, one should be guided by the requirements of SNiP III-18-75.

3.131. The cable guides for the supports must have an anti-corrosion coating. They must be made and marked before the towing of the supports to the track and delivered to the pickets, complete with supports.

3.132. The installation of supports on foundations that are not completed with a structure and are not completely covered with soil is prohibited.

3.133. Before installing the supports by pivoting using a hinge, it is necessary to provide for the protection of the foundations from shear forces. A braking device should be used in the direction opposite to lifting.

3.134. The nuts securing the supports must be tightened to the full and secured against self-loosening by punching the bolt thread to a depth of at least 3 mm. Two nuts should be installed on the bolts of the foundations of corner, transition, end and special supports, and one nut per bolt for intermediate supports.

When fixing the support on the foundation, it is allowed to install no more than four steel gaskets with a total thickness of up to 40 mm between the fifth support and the upper plane of the foundation. The geometric dimensions of the spacers in the plan must be at least the dimensions of the heel of the support. The gaskets must be welded together and the fifth support.

3.135. When installing reinforced concrete structures, one should be guided by the rules for the production of work set forth in SNiP III-16-80.

3.136. Before installing the reinforced concrete structures that arrived at the picket, it is necessary to check again the presence of cracks, cavities and potholes and other defects on the surface of the supports in accordance with paragraph 2.7.

In case of partial damage to the factory waterproofing, the coating must be restored on the track by painting the damaged areas with molten bitumen (grade 4) in two layers.

3.137. The reliability of anchoring in the ground of supports installed in drilled or open pits is ensured by observing the depth of embedding of supports, crossbars, anchor plates, as provided for by the project, and careful layer-by-layer compaction of the soil for backfilling the sinuses of the excavation.

3.138. Wooden supports and their parts must meet the requirements of SNiP II-25-80 and the draft of standard structures.

In the manufacture and installation of wooden poles of overhead lines, one should be guided by the rules for the production of work set forth in SNiP III-19-76.

3.139. For the manufacture of parts of wooden supports, timber should be used conifers according to GOST 9463-72 *, factory-impregnated with antiseptics.

The quality of impregnation of support parts must comply with the standards established by GOST 20022.0-82, GOST 20022.2-80, GOST 20022.5-75 *, GOST 20022.7-82, GOST 20022.11-79 *.

3.140. When assembling wooden supports, all parts must fit together. The gap in the places of notches and joints should not exceed 4 mm. The wood at the joints should be free of knots and cracks. Notches, grooves and spalls should be made to a depth of no more than 20% of the diameter of the log. The correctness of the cuts and grooves should be checked with templates. Through slots in the joints of working surfaces are not allowed. Filling gaps or other leaks between working surfaces with wedges is not allowed.

Deviation from the design dimensions of all parts of the assembled wooden support is allowed within the following limits: in diameter - minus 1 plus 2 cm, in length - 1 cm per 1 m. Minus tolerance in the manufacture of traverses from sawn timber is prohibited.

3.141. The holes in the timber support elements must be drilled. The hole for the hook, drilled in the support, should have a diameter equal to the inside diameter of the cut part of the hook shank and a depth equal to 0.75 times the length of the cut part. The hook should be screwed into the support body with the whole cut part plus 10-15 mm.

The pin hole diameter must be equal to the outer diameter of the pin shank.

3.142. Bandages for connecting attachments with a wooden support post should be made of soft galvanized steel wire with a diameter of 4 mm. It is allowed to use non-galvanized wire with a diameter of 5-6 mm for bandages, provided that it is coated with asphalt varnish. The number of turns of the band should be taken in accordance with the design of the supports. If one turn is broken, the entire band should be replaced with a new one. The ends of the wires of the bandage should be driven into the wood to a depth of 20-25 mm. It is allowed to use special tightening (bolted) clamps instead of wire bands. Each band (clamp) should mate no more than two parts of the support.

3.143. Wooden piles must be straight, straight-layered, free from rot, cracks and other defects and damage. The upper end of a wooden pile should be cut perpendicular to its axis in order to avoid deviation of the pile from a given direction during its immersion.

3.144. Tolerances for the installation of wooden and reinforced concrete single-post supports are given in table. 6.

3.145. Tolerances for the installation of reinforced concrete portal supports are given in table. 7.

3.146. Tolerances in the dimensions of the steel structures of the supports are given in table. eight.